Installation Guide for Comfort Pack (CPE) Units
Clearances
10
Comfort Pack
units must be installed through an outside wall. Confined spaces and/or covered areas
should be avoided. Consult the factory if unclear of clearances required. Units must be installed a minimum
of
12”
apart when two units are side by side. If three or more units are to operate next to one another, allow
a minimum of
60”
between units or pairs of units. Also, a vertical clearance of
60” should be maintained
between units. Units installed on the bottom floor should be mounted at least
8”off of the ground.
The unit is designed and approved for thru the wall installation only. The unit must be installed a minimum
of
8”
above a finished floor. If the unit is installed in a residential garage, it must be installed so that the
ignition source is located not less than
18”
above the floor, and it must be located or protected to avoid
physical damage by vehicles.
For proper unit performance and
maximum operating life please
maintain the following minimum
installation clearances.
Minimum 12”
Horizontal Clearance
Between Units
*Less than 12” Call National Comfort Products
Minimum 60”
Vertical Clearance
Between Units
Summary of Contents for Comfort Pack CPE U Series
Page 21: ...Installation Guide for Comfort Pack CPE Units 19 U 11 Wiring Schematic Electric Heat 5 7 10Kw...
Page 22: ...Installation Guide for Comfort Pack CPE Units 20 U 11 Wiring Schematic Electric Heat 15Kw...
Page 23: ...Installation Guide for Comfort Pack CPE Units 21 U 12 Wiring Schematic Electric Heat 5 7 10Kw...
Page 24: ...Installation Guide for Comfort Pack CPE Units 22 U 12 Wiring Schematic Electric Heat 15Kw...