9
Installation and operation manual
–
DTHR-V9-2020
IMPORTANT NOTICE
The below drawings show the recommended walls arrangements and inlet/outlet configuration that we
have tested and believe will be safe. If the OEM decides to assemble the units with different wall and
opening parameters, it will be his responsibility to test for safety and functionality.
Horizontal discharge
Step 1:
•
Install the unit on an insulated floor
Step 2:
•
Install walls on each side (see dimension table);
•
The walls must be in contact with the guides on the
support structure;
•
The walls must be insulated with 2’’ of high temperature
insulation.
Step 3:
• Install the air baffle on the internal side of the roof;
•
Put the roof in place.
• The walls must be insulated with 2’’ of high temperature insulation.
Step 4:
•
Seal and caulk with high temperature sealant.