VERTICAL INSTALLATION
figure D
figure A
C
figure F
WALL
figure B
WALL
BASE
Anchor bolts
3/8’’
(not supplied)
OPTION (suggestion)
Installation of wall rail
-
Align
wall rail (not included) to the holes of
the return brackets (figure F).
-
Make sure
the rail is parallel.
-
Secure
the rail to the wall or any solid stucture
-
Secure
the return brackets to the rail.
figure E
figure C
Door rail
1 in.
(25.4 mm)
1/2 in. (12.7 mm)
Base
ground
C
WALL
figure D
Return brackets
3
The base
Position the base
at a minimum of 1 in. (25.4 mm)
from the wall and at 1/2’’ (12.7 mm) from the front of
the door rail ( figure A )
-
Identify
,
mark
and
drill
four (4) anchor holes on the
floor.
-
Insert
the anchor bolts 3/8’’ (not supplied) in the
floor.
-
Make
sure base is level and then
secure
. ( figure B)
Air curtain installation
-
Carefully lift
the air curtain and
Insert
it into the
base.
- Using the hardware supplied,
secure
the air curtain
to the base (figure C)
Wall mounting system
-
Attach
brackets on the top of air curtain with
supplied bolts as illustrated in figure D.
-
Verify
that return brackets are facing the wall.
Note : The empty hole can be used to lift the unit into
place.
- Secure
the return brackets with threaded rods (not
supplied) to the wall. (figure D, E)
-
Make sure
the air curtain is level.
Superimposing 2 air curtains
-
Attach
new brackets on top of the second air
curtain with supplied bolts as illustrated in figure D.
-
Verify
that return brackets are facing the wall.
-
Carefully lift
second unit into place using empty
holes in brackets if necessary.
-
Place
unit on top of first unit inside the brackets
(figure E)
-
Secure
the air curtain to the brackets using bolts
supplied.
-
Verify
that return brackets are facing the wall.
-
Make
sure air curtain is level and then
secure
the
brackets with threaded rods (not supplied) to the
wall.