- 5 -
IV. Installation
1. Check before Installation
After the analyzer is unpacked, check the analyzer and all the parts specified
in the manual and check if there are any damages. If so, please contact the
manufacturer in time (please keep the damaged parts).
2. Conditions for Installation
(1). This analyzer should be placed away from direct sunshine, moisture,
heat and coldness,Generally room temperature should be kept between
10
℃
~ 28
℃
.
(2). This analyzer should be placed near water source and sinks, and electric
socket should be available at the site. The distance between the instrument
and water tap (or the power socket) should not be over 1 meter to ensure
convenience of operation. The water should meet the following requirements:
water flow 1-2 liter per minute, adequate water pressure and temperature no
more than 20
℃
.
(3). The sink should be at least 10cm lower than the water outlet of the
instrument to ensure free flow of the water.
(4). The power supply should meet the requirement. Ground line, separate
power switch and right fuse are necessary to make sure the safety of the
operators.
(5). This analyzer should be installed at the place where there is no big
electrical equipment nearby and the working place should be free of vibration,
corrosive liquid and interference from strong electromagnetic field.