▷ The
Rear support
must be fixed to
the pillar or wall using dimensions
provided in the preceding pages.
It can be fixed using screws with
mechanical bushing or chemical
welding process, or one of your choice
since it provides an appropriate
support.
01
- Fixing rear support
02
- Fixing front support
▷ The
Front support
should be fixed to
the gate, respecting height dimensions
and distance to the rear support.
This may be fixed by using screws,
welding process, or to choose another
long as it provides a secure proper
support.
03
- Remove caps and pins from motor
▷ Before installing motor, remove caps
and pins from motor.
▷ At the end of the installation, put
back plastic covers for a better visual
finish of the operator.
▷ The operator must be placed on both
supports the same time to avoid leaving
the operator suspended by only one of
the supports.
To make the task easier, you should
unlock the operator in order to be able
to stretch / retract arm easily (see page
03.B),to get the correct position for
supports.
04
- Install operator on the supports
05
- Test movement
▷ Install the pins removed earlier on each
place with a small amount of lubricant
for less friction.
▷ Move the door manually to see if the
door opens and closes uniformly and
correctly, without any irregular friction
during its entire travel;
This will ensure that operator is not
subjected to problems during operation.
06
- Connecting operator to control
board and configuring control devices.
▷ With the operator installed, connect
it to control board for system configura-
tion (see control board user manual).
Must also configure the desired control
devices (transmitters, wall switch, etc.)
and other additional components such
as antenna, warning light, key selector,
among others.
04
.
INSTALATION
▷ INSTALLATION STEPS
INSTALLATION STEPS ◁
04
.
INSTALATION
06.A
06.B
Pay attention to installation dimensions mentioned on pages 04.B,
05.A and 05.B!
It is important to respect this installation order!
Otherwise, it is not possible to ensure correct installation and operators may not
work properly!