Moog Videolarm P1800 Installation And Operation Instructions Manual Download Page 5

3.  

FOR ANCHOR BOLT INSTALLATIONS:

  

Pour concrete per manufacturer's directions, making sure that the wiring conduit 
is in the center of the pad. See Figure 3 for dimensions of the bolt pattern and 
suspend appropriate bolts in the concrete around the wiring conduit.  Leave 2" to 3" 
of the 

Bolts

 protruding above the pad.  If you are using leveling nuts, leave 4" to 6" 

protruding. 

Prepare the concrete per manufacturer's directions.  The 
concrete must have a compressive strength of 3000 psi, and 
must be fabricated following ACI318-89 requirements.  Allow 
the concrete foundation to cure thoroughly before proceeding 
with the installation.

Schematic view of 
concrete foundation

Figure 3

FOR ANCHOR JIG INSTALLATIONS:

Suspend the assembled Anchor Jig in the center of the pad hole (see Figure 2, 
previous page).  Leave 2" to 3" of the Bolts protruding above the pad (unless you're 
using leveling nuts, see Anchor Jig instructions).  Make sure that the Conduit is in the 
center of the Anchor Jig.  Both the jig and the conduit must be securely suspended to 
prevent shifting when the concrete is poured.

!

Figure 4

Part 2:  Installation

1.  Assemble the pole and transformer base using the bolts, nuts, and washers 
provided (Figure 5). 

Figure 5

Access opening plates

Figure 6

3.000

O

11.000

O

4X

1.000

O

4.000

4.000

7.778

7.778

13.000

13.000

BASED ON A 11.00" B.C.

 4 x O 1"
Based on an 11" B.C.

7.778"

4"

4"

O 3"

13"

13"

7.778"

O 11"

Top access opening

2.  Remove the access opening plates at the bottom and top (Figure 6).

3.  Insert the wiring into the transformer base, up into the pole and out of the bottom 
access opening.  Make sure all slack is pulled completely through.

4.  Insert connecting wiring into the bottom access opening, run through the pole up 
to the top access opening.  Insert the end through the housing connecting hole.  Close 
the top access opening and make necessary wiring connections at the bottom access 
opening (Figure 6).

Summary of Contents for P1800

Page 1: ...Bracket Mounts and Poles Installation and Operation Instructions Before attempting to connect or operate this product please read these instructions completely 81 IN5233 12 21 2011 2011 Moog Videolarm...

Page 2: ...onents can be damaged if improperly handled or dropped If an item appears to have been damaged in shipment replace it properly in its carton and notify the shipper Be sure to save 1 The shipping carto...

Page 3: ...pect to any Product requiring service during the warranty period which is subjected to any of the following abuse improper use negligence accident lightning damage or other acts of God i e hurricanes...

Page 4: ...center of the foundation and Anchor Jig during installation Figure 1 1 diameter maximum Figure 1 Figure 1 Wiring conduit 1 Select a suitable site for the P1600 and prepare the pad site using a hole 3...

Page 5: ...ad unless you re using leveling nuts see Anchor Jig instructions Make sure that the Conduit is in the center of the Anchor Jig Both the jig and the conduit must be securely suspended to prevent shifti...

Page 6: ...he pole is vertical on all sides Use a bubble level or plumb bob to check 6 Secure the pole to the pad with fasteners Figure 8 5 Place the pole on the pad with the holes on the Transformer Base aligne...

Page 7: ...o the power transformer Make the appropriate connections Run video and control into the NEMA box through the conduit opening closest to the surge protector Connect video output to the surge protector...

Page 8: ...ing Power 1 2 3 4 5 6 24 VAC power pre connected 1 RED RX Control Data 2 ORANGE RX Control Data 3 YELLOW TX Control Data 4 GREEN TX Control Data 5 BLUE Alarm 6 GRAY Alarm User Wiring Connections Video...

Page 9: ...center dimensions between the bolts are even Figure 4 If not adjust accordingly Firmly tighten all Hex Nuts With Leveling Nuts Without Leveling Nuts 11 2 6 18 Figure 1 1 1 2 2 Place the short end of...

Page 10: ...ousings Poles Power Supplies and Accessories and 5 Years on camera systems SView QView Warriors and InfraRed Illuminators Register Your ProductsOnline Take a few moments and validate your purchase via...