STANDARD INSTALLATION PROCEDURE

INCLUDES MODELS:  P1800

!

NOTE:  If you'll be using the optional PV4 anchor  jig, see 
the attached instructions for assembly of the jig.

Part 1:  Site Preparation

!

NOTE:  

Special attention must be paid to the size of the wiring 

conduit and its location within the  concrete foundation and jig (if 
applicable.)   The 

Wiring Conduit

 can be up to 2" in diameter.  

Use reducers if necessary.  Also, make sure that the 

Wiring 

Conduit

 is in the center of the foundation and 

Anchor 

Jig

 during installation (Figure 1). 

1" diameter

maximum

Figure 1

Figure 1

Wiring conduit

1.

  

Select a suitable site for the P1600

 

and prepare the pad site using a hole 36" 

x 36" x 36" deep.  The top of the concrete foundation should be flush with the 
ground. 

CALL BEFORE DIGGING!  Be sure that there are no 
underground electric or phone cables, gas or water 
lines in the area where the pole will be located.

!

2.  To help reinforce the concrete foundation, place (12) 1/2" diameter x 32" long 
Reinforcement Bars ("rebar") as shown in Figure 2.  Use suitable preparation 
methods to place the rebar. 

24"

36"

24"

36"

24"

6"

24"

6"

32"

32"

8"

8"

12"

12"

32"

36"

Figure 2

Reinforcement bars (12)

PV4 Anchor jig (if applicable)

Up to 2" in 
diameter

Summary of Contents for P1800

Page 1: ...Bracket Mounts and Poles Installation and Operation Instructions Before attempting to connect or operate this product please read these instructions completely 81 IN5233 12 21 2011 2011 Moog Videolarm...

Page 2: ...onents can be damaged if improperly handled or dropped If an item appears to have been damaged in shipment replace it properly in its carton and notify the shipper Be sure to save 1 The shipping carto...

Page 3: ...pect to any Product requiring service during the warranty period which is subjected to any of the following abuse improper use negligence accident lightning damage or other acts of God i e hurricanes...

Page 4: ...center of the foundation and Anchor Jig during installation Figure 1 1 diameter maximum Figure 1 Figure 1 Wiring conduit 1 Select a suitable site for the P1600 and prepare the pad site using a hole 3...

Page 5: ...ad unless you re using leveling nuts see Anchor Jig instructions Make sure that the Conduit is in the center of the Anchor Jig Both the jig and the conduit must be securely suspended to prevent shifti...

Page 6: ...he pole is vertical on all sides Use a bubble level or plumb bob to check 6 Secure the pole to the pad with fasteners Figure 8 5 Place the pole on the pad with the holes on the Transformer Base aligne...

Page 7: ...o the power transformer Make the appropriate connections Run video and control into the NEMA box through the conduit opening closest to the surge protector Connect video output to the surge protector...

Page 8: ...ing Power 1 2 3 4 5 6 24 VAC power pre connected 1 RED RX Control Data 2 ORANGE RX Control Data 3 YELLOW TX Control Data 4 GREEN TX Control Data 5 BLUE Alarm 6 GRAY Alarm User Wiring Connections Video...

Page 9: ...center dimensions between the bolts are even Figure 4 If not adjust accordingly Firmly tighten all Hex Nuts With Leveling Nuts Without Leveling Nuts 11 2 6 18 Figure 1 1 1 2 2 Place the short end of...

Page 10: ...ousings Poles Power Supplies and Accessories and 5 Years on camera systems SView QView Warriors and InfraRed Illuminators Register Your ProductsOnline Take a few moments and validate your purchase via...