![Moog Videolarm P1800 Installation And Operation Instructions Manual Download Page 4](http://html1.mh-extra.com/html/moog-videolarm/p1800/p1800_installation-and-operation-instructions-manual_1831912004.webp)
!
Please read these instructions carefully before proceeding,
and heed all cautions.
STANDARD INSTALLATION PROCEDURE
INCLUDES MODELS: P1800
!
NOTE: If you'll be using the optional PV4 anchor jig, see
the attached instructions for assembly of the jig.
Part 1: Site Preparation
!
NOTE:
Special attention must be paid to the size of the wiring
conduit and its location within the concrete foundation and jig (if
applicable.) The
Wiring Conduit
can be up to 2" in diameter.
Use reducers if necessary. Also, make sure that the
Wiring
Conduit
is in the center of the foundation and
Anchor
Jig
during installation (Figure 1).
1" diameter
maximum
Figure 1
Figure 1
Wiring conduit
1.
Select a suitable site for the P1600
and prepare the pad site using a hole 36"
x 36" x 36" deep. The top of the concrete foundation should be flush with the
ground.
CALL BEFORE DIGGING! Be sure that there are no
underground electric or phone cables, gas or water
lines in the area where the pole will be located.
!
2. To help reinforce the concrete foundation, place (12) 1/2" diameter x 32" long
Reinforcement Bars ("rebar") as shown in Figure 2. Use suitable preparation
methods to place the rebar.
24"
36"
24"
36"
24"
6"
24"
6"
32"
32"
8"
8"
12"
12"
32"
36"
Figure 2
Reinforcement bars (12)
PV4 Anchor jig (if applicable)
Up to 2" in
diameter