4.  Replace container and switch on. 

5.  Turn Bain-Marie control knob to No. 3 (No. 3 is full on). 

6.  Turn Hot-Cupboard control knob to 110°C. 

7.  Leave to heat up for approximately 45 minutes 

before filling containers with cooked food produce.

The correct serving temperature is dependant on 
the food type, amount of food in container, etc. Do 
not remove lids until service is due to commence.

8.  After 45 minutes, adjust control knobs to the desired settings. 

Recommended settings are Bain-Marie 2 or 3 and Hot-Cupboard to 90°C. 

9.  When serving is complete, all switches should be turned off. 

10. To maintain the life of this product, all surfaces need 

cleaning regularly with a damp cloth.

Dry Heat:

Dry heat works in the same way without any water in the 
well. Heat up time will be around 30 min.

The base of the well will distort slightly and discolour 
when used dry. This is normal.

Draining well:

1.  Switch off & disconnect unit from mains power, 

then wait until water cools down to room temperature. 

2.  Open to the hot cupboard left hand door fully & securely 

place a suitable size container under the flexible drain hose. 

3.  Open drain valve & fill container. 

4.  Switch off valve & empty container when full 

in a suitable place. Repeat until well is empty. 

5.  Close drain valve then close hot cupboard door. 

6.  The well can now be cleaned (See page 12 for cleaning instructions).

Summary of Contents for HB2E

Page 1: ...Manual 003 Issue 001 October 2019 Operating Service Manual Premier Hot Cupboard Bain Marie Hot Cupboard...

Page 2: ...ormation required to place the call Check warranty maintenance terms and conditions To ensure the best results from this unit please take the time to read and follow all safety installation and mainte...

Page 3: ...3 Contents Electrical Operation Door Installation Removal Sahara Fan Installation Removal Bain Marie Operation Specifications Dimensions 1 2 3 4 5 6 page 4 6 7 8 10 12...

Page 4: ...ed fused 13 amp plug BS 1363 Warning Damaged supply cords must be replaced before use These units are designed for connection to a single phase AC supply The wires are coloured with the following code...

Page 5: ...ation may be fitted with either an isolator or MCB unit In accordance with health and safety at work acts BS codes of practice IEE regulations building standards fire precautions act and local authori...

Page 6: ...ep Doors Closed at all times only opening to load unload cupboard contents Before using the unit for the first time it needs to be checked that it s perfectly level Hot storage cupboard with removable...

Page 7: ...e it fully to the right Note It s imperative the doors must be fitted in correct order as shown in fig 2 Door A first then Door B Door removal is a reverse of the above 4 After this time period has el...

Page 8: ...he Male plug fitted to the Sahara fan unclip as shown in fig 4a 2 Prise the female socket off the plug fig 4b 3 Remove as many rodded shelf sections as needed to allow access to the Sahara fan Lift ou...

Page 9: ...9...

Page 10: ...0mm deep These units are not designed to cook raw food or to heat up cold food E R Moffat Ltd were the originators of a Bain Marie that could be either wet or dry heat This type of system was designed...

Page 11: ...d off 10 To maintain the life of this product all surfaces need cleaning regularly with a damp cloth Dry Heat Dry heat works in the same way without any water in the well Heat up time will be around 3...

Page 12: ...5 1 9 2 Electrical Supply 13amp 13amp 13amp 13amp 13amp Hot Cupboard Bain Marie Wet Heat Model HB2E HB3E HB4E HB5E HB6E Weight kg 65 81 100 118 138 Length 884 1212 1540 1865 2196 Width 750 750 750 750...

Page 13: ...13...

Page 14: ...fat Ltd Bonnybridge FK4 2BS Scotland Scan the QR code below to visit the E R Moffat website for further information www ermoffat co uk 44 0 1324 812272 sales ermoffat co uk Thank you for choosing E R...

Reviews: