• Connect the luminaire to the mains supply via a suitable junction box (not included) ensuring the correct
polarity is observed: L - Live (brown), N - Neutral (blue)
• Connect the battery via the plug and socket to the inverter
• Place the battery and inverter into the ceiling void ensuring that there is at least 50mm
of clearance above and around them
• Lift both of the spring clips on the sides of the luminaire and push into the ceiling
• Switch on and check for correct operation, ensuring the green indicator LED is illuminated
• We recommend, on commissioning the installation, a minimum charge period of 24 hours before carrying
out an emergency duration test
• If the batteries have been left in a discharged state for an extended period, we recommend that one or
more charge and discharge cycles are completed which should help to restore the battery capacity
Fig. 1