Installationsplan / Installation plan: PT 8803/8805/8807
Datum / Date: 12.01.2011
Seite / Page: 9
Technical datasheet
Tumble dryer:
Heating:
PT 8803/8805/8807
Electric (EL)
Legend:
Abbreviations in bold type:
Connection required
en - GB
Abbreviations in circle with dashes:
Connection optional or required depending on model version
Optional extras:
BS
Concrete plinth
Quality and density of concrete must comply with load.
Concrete plinth must be firmly secured to floor!
Recommended height
mm
100
Minimum height
mm
50
Width min.
mm
1200
Width:min.
mm
1400
Machine connections:
Electrical
connection
1. Standard voltage (as supplied)
V
3N AC 380 - 415
Frequency
Hz
50
Rated load
kW
34.4 – 40.7
Fuse rating
A
3 × 63
Connection cable, min. cross-section
mm²
5 × 16
Cable screw connector
M 50
Connection cable (to be ordered separately)
2. Standard voltage (as supplied)
V
3 AC 220 - 240
Frequency
Hz
50
Rated load
kW
34.8 – 41.1
Fuse rating
A
3 × 100
Connection cable, min. cross-section
mm²
4 × 25
Cable screw connector
M 50
Connection cable (to be ordered separately)
Non-standard voltages:
OS 440
Standard voltage (as supplied)
V
3 AC 440
Frequency
Hz
60
Rated load
kW
37.9
Fuse rating
A
3 × 63
Connection cable, min. cross-section
mm²
4 × 16
Cable screw connector
M 40
Connection cable (to be ordered separately)
Electrical connection must comply with national regulations.
Connection using multi-pole wall socket in compliance with
IEC/EN 60309 and IEC/EN 60947 is recommended in order to
simplify electrical tests.
If machines are hard-wired, a multi-pole mains switch must be
provided on site.
A wall socket or mains isolator must be accessible after
installation.