Rack Installation
System Installation
2-4
DAR Plus Operator’s Guide
400468-1
Rev. C
2.3
Rack Installation
The DAR PLus mounts within a standard 19 inch equipment rack. The unit occupies a
height 3 rack units (3RU). The DAR PLus attaches to the equipment rack using four 12–24
mounting screws. See
for the correct mounting hole locations.
Figure 2-2
Rack Installation
For detailed information on assembling and installing a standard equipment rack, see
Section 2.4, Equipment Rack Installation on page 2-4
2.4
Equipment Rack Installation
Step 1
Remove the top and sides of the shipping container and packaging material, free
the rack from the pallet by removing the nuts and bolts securing it in place. Refer
to
for equipment rack specifications.
Table 2-1
Equipment Rack Specifications
Step 2
Remove the rack from its crate by lifting it off the mounting bolts and place it
near its final mounting location. After the rack has been raised to a vertical
position, remove the shipping support brackets the rack side rails.
Step 3
A template can be used for marking the floor location drilling holes for anchoring
the hardware (
). However, if the rack is available when these holes are
drilled, it is recommended that the rack base itself be used as a template.
Component
Description
Finish
Black baked enamel
Uprights Channel
3.0” (76.20 mm) deep x 1.4” (34.825 mm) wide x 0.25” (6.35
mm) thick.
Base Angles
4.0” (100.016 mm) high x 6.5” (162.40 mm) deep x 0.38” (9.50
mm) thick.
Top
1” (25.40 mm) high x 0.38” (9.50 mm) thick.