4.2
Power-Up Test
4.2.1
After performing the Battery Scan Procedure above, set all battery circuit breakers to
the “ON” position.
4.2.2
Allow the UPS to charge the batteries for at least 3 hours per battery pack. You may
use the UPS while the batteries charge, but the battery backup runtime will be reduced
until the batteries are fully charged.
4.2.3
Switch on the protected equipment, one load at a time. If the UPS beeps an alarm
when you start your equipment, the UPS may be overloaded.
4.2.4
The four LEDs on the right side of the front of the UPS show the percent of battery
capacity remaining. To verify the percentage of maximum load, depress the “Push for %
of load” button.
Successful completion of the procedures above will verify that the Comet EXtreme
UPS is properly configured and ready for use. Please refer to your user guide for
detailed information on the function of your UPS.