34
INSTRUCTION MANUAL
–
T229, T241 FRONT LOADER
4. Ongoing Control and Adjustment Components
4.1 Front Loader Joystick
Install the Loader controller (joystick) inside the cab and connect it to the electrical system
of the tractor using the Loader socket.
The wiring diagram of the joystick is shown in figure 15.
Connect the joystick to the two-section valve block installed on the support frame with
Bowden cables.
Figure 15.
Joystick
wiring diagram
4.2 Arrangement of Adjustment Controls
The level indicator of the Loader must be adjusted after each tool installation. Procedure:
−
set the tool in the desired working position,
−
unlock the support (1),
−
set the support (2) placing its centre in the middle of the yellow indicator,
−
lock the support (1).
The first installation of the Loader controller must be
performed in an authorised service centre of the
dealer/manufacturer.
Push button
Joystick
Soldered cube
Protection device
Battery
Bundle
Plug
Line
Line
Line
Red "+"
Brown "-"
Red and Black "+"
LED
Joystick
wiring diagram
Summary of Contents for T229
Page 2: ......
Page 60: ...60 INSTRUCTION MANUAL T229 T241 FRONT LOADER NOTES...
Page 61: ...INSTRUCTION MANUAL T229 T241 FRONT LOADER 61...
Page 62: ...62 INSTRUCTION MANAL T229 T241 FRONT LOADER...
Page 63: ......