12
the fuel and slag store should be located by the boiler room. The storing height up to 220
cm with a 50 cm free space above it.
the equipment for vertical and horizontal delivery of the fuel and slag should be considered.
the fuel store should be equipped with natural ventilation that allows for full airing once an
hour in the fuel store and three airing circles an hour in the slag store.
the entrance door to the boiler room should be fire- resistant (0,5 class of fire resistance),
the minimum width 80cm and should open outside. the door should have a handle- free
system when opened from the inside and have a door handle when coming inside
the requirements for the ventilation are the same as those for the boiler rooms of lower
power; additionaly, in the boiler rooms of power greater than 400 kW, the supply exhaust
ventilation should be accompanied by mechanical ventilation that can be periodically
activated when feeding the fuel and removing slag. it must also be able to provide 10 airing
circles an hour
natural lightning which can light the front of the boiler should be considered in the room.
the total surface of the windows should equal at least 1/15 of the floor surface; half of the
windows in the room should open; the electrical lightining and electrical socket of max. 24 V
should also be located in the room
inspection chamber that will allow cooling water should be located in the floor; its capacity
should equal the water capacity of the biggest boiler but not exceed 2m3
in the boiler room all the heating pipes should be insulated
The placing of the boiler together with the minimum distance requirements is presented in
the boiler room (Schematic 14.1)
ATTENTION!
The mechanical exhaust ventilation should not be used in the boiler room
ATTENTION!
Correct fresh air infeed to the boiler room will ensure efficient fuel burn.
ATTENTION!
Ensure that the carbon dioxide level in the room is not too high.
ATTENTION!
For more information on boiler room construction, refer to the 12.03.2009 Minister
of Infrastructure Law.
TIP!
The rules included in the law serve only as guidelines which must be verified as the
law is amended.
Schematic 14.1 Minimal requirements for the boiler room
15.
Boiler installation
(USER/INSTALLER)
The important element of installation is correct setting and levelling of the SEG BIO boilers. The
boilers do not require special base and need to be leveled with adjustable feet. The boiler must be
set in the vertical position.
1.
Check that four adjustable feet have been provided
Summary of Contents for SEG BIO 100
Page 31: ...30 TROUGH BURNER...
Page 42: ...41 11 12 13 14 15 16 17 18 19 20 21...
Page 43: ...42...
Page 45: ...44...
Page 47: ...46...
Page 49: ...48...