14. Press the grey CONTINUE button to advance to the flow calibration menu. The pump will
start automatically and adjust flow to the 16.7 lpm test point.
15. Press the green bordered value box the flow rate test set point selection will appear.
16. Select the 14.0 lpm set point and then press the OK button. The display will return to the
Flow Calibrate screen and adjust the flow to the new test point.
17. Allow the E-BAM and CTS reading to stabilize (at least one minute) and then compare the E-
BAM flow measurement and CTS flow reading.
18. If the E-BAM flow rate exceeds the criteria listed in Table 5-3, press the grey DEFAULT
button to remove any previous offsets for all three flow settings. If the flow rate now passes,
skip the next step.
19. If the flow rate still needs to be adjusted, press the green bordered value box and the
numerical entry keypad will be displayed. Enter the CTS value in the Standard field, and
press OK to return to the Flow Calibrate screen. Press the grey CALIBRATE button to enter
the new calibration offset.
20. Press SET to apply the change. When setting the 16.7 lpm flow rate, the SET option will
change to read CALIBRATE.
21. Repeat steps 15 through 18 above for the 17.5 lpm flow rate.
22. Repeat steps 15 through 18 above for the 16.7 lpm flow rate.
23. Return to the Main Operating Screen and remove the CTS from the inlet tube and replace
the size selective inlet(s).