Step 17

Cut the felt into 3 strips

and place onto the roof,

as shown in the illustration.

Fix the sheets into place

using 132x felt tacks

approximately 100mm

apart.

132x Felt Tacks

Felt 

tacks 

P 6

Please retain product label and instructions for future reference

             

Please retain product label and instructions for future reference

             

Step 14

Repeat Steps 11, 12 & 13 to

finish building the roof support.

4x40mm Screws

16x50mm Screws

Pre drill 

hole

40mm 

screw

50mm 

screw

13

8

Step 15

Place the first roof sheet on to

the building, securing in place

with 11x30mm screws.

 

Fix the first eaves frame

 

onto the roof sheet,

 

seceuring with 3x30mm

 

screws.

Fix the remaining roof sheets to

the building using 11x30mm

screws per sheet.

 

Fix the next eaves frame

 

to the roof with 3x30mm

 

screws.

 

Secure the remaining eaves

 

frame to the center using

 

6x30mm screws.

64x30mm Screws

c

c

Pre drill 

hole

30mm 

screw

*Repeat this process for both sides of the building, ensuring

the roof sheets are flush to the top of the building and sit 

tight together.

Step 16

 

Secure the building to

 

the floor using 38x50mm

 

screws.

*Ensure to screw through the

framing into the floor bearers.

38x50mm Screws

Pre drill 

hole

50mm 

screw

HANDLE

WITH CARE

1

2

3

4

13

13

*Felt size: 3150mm

Summary of Contents for Vermont 03VER0808-V1

Page 1: ...o ensure the product is placed on a suitable base BUILDING A BASE When thinking about where the building and base is going to be constructed Ensure that there will be access to all sides for maintenance work and annual treatment Whilst all products manufactured are made to the highest standards of Safety and in the case of childrens products independently tested to EN71 level we cannot accept resp...

Page 2: ... building MADE IN GREAT BRITAIN Door Panel Sml Panel QTY 2 Window Panel Right Window Panel Left Back Panel QTY 2 Gable Top QTY 2 Floor QTY 2 Roof Sheet QTY 4 Master Door Slave Door Side Door Ridge Bar 1462mm QTY 2 Eaves Frame 1001mm QTY 6 Roof Support Bar 1302mm QTY 6 Roof Support Brace 490mm QTY 6 16 Cover Trim 1976mm QTY 7 17 Fascia 1333mm QTY 4 18 Finial QTY 2 19 Rain Guard 680mm QTY 2 Pre Asse...

Page 3: ...ore fixing to the door Fix the door handles to the outside of the master and slave door using the 35mm bolts provided 36x10mm Screws 4x25mm Screws 4x35mm Bolts Pre drill hole 10mm screw 25mm screw 24 Step 4 Place the floor panels upside down onto a firm and level base Ensure the base has suitable drainage free from areas where standing water can collect Secure the floors together using 8x50mm scre...

Page 4: ...e roof is fitted 9x50mm Screws Pre drill hole 50mm screw 5 4 Step 8 Place the gable tops onto the window panels ensuring the boards interlock Secure in place using 4x50mm screws per gable top screwing in an alternating pattern 8x50mm Screws Pre drill hole 50mm screw Step 9 Connect the ridge bars together with the metal U channel using 10x30mm screws Attach the L brackets to each end of the bunk su...

Page 5: ...rs into the ridge bar with 1x50mm screw per bar screwing at an angle as shown in the illustration Ensure to stagger the screws so as not to hit one screw with another 2x50mm Screws Pre drill hole 50mm screw Step 12 Fix the roof support blocks centrally to the back and door panel upright framing with 2x50mm screws per block Ensure the roof support bars meet the blocks and are level with the gables ...

Page 6: ...ilding securing in place with 11x30mm screws Fix the first eaves frame onto the roof sheet seceuring with 3x30mm screws Fix the remaining roof sheets to the building using 11x30mm screws per sheet Fix the next eaves frame to the roof with 3x30mm screws Secure the remaining eaves frame to the center using 6x30mm screws 64x30mm Screws c c Pre drill hole 30mm screw Repeat this process for both sides ...

Page 7: ... to the front and back of the building using 12x40mm screws 12x40mm Screws Pre drill hole 40mm screw Step 20 Fix the rain guards above each window securing in place using 2x50mm screws per guard ensuring to screw through the framing 4x50mm Screws Pre drill hole 40mm screw Step 21 Attach the two turn buttons to the slave door at the top and bottom using 2x30mm black screws 2x30mm Black Screws These...

Page 8: ...apply wood treat ment immediately after the building has been assembled AFTER TREATMENT score around protective cover on glazing and carefuly peel covering back Please retain product label and instructions for future reference ...

Reviews: