Assembly
Nail Bag & Ironmongery
30mm Screw x75
50mm Screw x 30
60mm Screw x2
20mm Screw x25
40mm Screw x25
Felt Tacks x120
Wooden door
handle
Felt
16
70mm Screw x8
Hinge x 2
17
18
30mm Black Screw x 14
Lay the door gable face up on a flat surface, place the door within the door aperture. Position the
door so that you have a equal gap either side of the door to the gable.
Once you are happy the door is in the correct position place a hinge at the top and bottom of the
door, ensuring the screws will go into the framing (in cases where you have been supplied three
hinges use the third in the middle of the door) and using 30mm black screws fix the hinge to the door
and the door gable. Ensure to pre-drill the holes first.
30mm Black Screw x 14
18
Remove transportation blocks
from the bottom of each panel
before beginning assembly. Each
Panel should have two blocks.
Step 1
Place the floor on a firm and level base,
ensure base has suitable drainage free
from areas where standing water can
collect. (See front page on base
requirements).
Step 2
11 x 50mm screws
Fix the corners with 3 x 50mm
screw as shown in diagram.
Do not secure the building to the
floor until the roof is fitted. Fix
the panels onto the floor using
50mm screws in alignment with
the floor joists
Side
Back
50mm
screw
4
2
50mm
screw
3