Step 3

 

Fix the door strips onto the front gable 

using 4x30mm screws for each strip.

4x30mm screws. 

30mm 

screw

Pre drill 

hole

15

5

5

25

Step 4

 

Fix the T Hinges onto the doors and 

door frame as shown above. Ensure 

that each of the hinges are evenly 

spaced and screwed into the Door 

framing. 

Make sure the framing of the doors 

points outwards to ensure rigidity.

42x30mm screws. 

30mm 

screw

Pre drill 

hole

3

4

Step 5

Lay the plain back panel and the remaining 

gable top on a level floor place the gable 

top on top of the plain back panel ensure 

they are level at the top then fix together 

using 60mm screws. Stagger the screws so 

they do not collide.

8x60mm Screws

Pre drill 

hole

60mm 

screw

12

Step 6

Line the remaining Gable Strip up to the 

assembled gable. Ensure the bottom of 

the strip lines up with the underneath of 

the plain back panel framing as shown in 

the illustration and fix in place using  40mm 

screws.

6x40mm Screws

Pre drill 

hole

40mm           

screw

Summary of Contents for 01DTGRODB0808-V3

Page 1: ...water during extended periods of warm sunshine and sheltered as much as possible during rain or snow Once your garden building has been installed it will need to be treated as soon as possible and an...

Page 2: ...45 x 1449mm QTY 1 S1245 1449MM Barge Board 12 x 95 x 691mm QTY 1 S1295 G 691MM Barge Board 12 x 95 x 760mm QTY 2 S1295 G 760MM Fascia Board 12 x 95 x 835mm QTY 4 S1295 G 835MM Fascia Board 12 x 95 x 7...

Page 3: ...or future reference Step 1 Lay the Door Panel and Gable Top on a level floor place the gable top on top of the door panel ensure they are level at the top then fix together using 60mm screws Stagger t...

Page 4: ...ds to ensure rigidity 42x30mm screws 30mm screw Pre drill hole 3 4 Step 5 Lay the plain back panel and the remaining gable top on a level floor place the gable top on top of the plain back panel ensur...

Page 5: ...g 4x30mm screws Ensure to screw through the window into the panel framing 4x30mm Screws b a 10 Opening Window Fixed Window 30mm screw 30mm screw 16mm screw 30mm screw 22 16 Pre drill hole a b Pre dril...

Page 6: ...ng fits into slot at top between the gable top rafters Fix panels into position using 4x30mm screws from the top of panel straight into the rafter Pre drill holes before hand Ensure the larger over ha...

Page 7: ...3 Step 15 Use 3x30mm screws to fix each cover trim 12x30mm screws Pre drill hole 30mm screw 20 19 Step 16 Fit fascia boards to the front and the back of building using 3x40mm screws per board as shown...

Page 8: ...aple to the Door Gable or secondary door Making sure the Hasp is in line with the staple and screw into the Door or Master door To lock the Door place the Hasp over the Staple and twist into the lock...

Page 9: ...el and instructions for future reference It is ESSENTIAL that you apply wood treatment immediately after the building has been assembled AFTER TREATMENT score around protective cover on glazing and ca...

Page 10: ...2 1 3 4...

Page 11: ...1 2 REGISTER FOR YOUR ANTI ROT GUARANTEE TODAY PLEASE SCAN HERE...

Reviews: