Installation manual
M-WRG-II M-U
2
- 21 -
Meltem Wärmerückgewinnung GmbH & Co. KG
Am Hartholz 4 · D-82239 Alling
[email protected] · www.meltem.com
VENTILATION THE RIGHT WAY
V E N T I L A T I O N & H E A T R E C O V E R Y
►
Break through the wall. There are two possible versions of the wall breakthrough:
—
Wall breakthrough with recess (see Fig. 9 on page 20) for installation kit
without
filler piece M-WRG-II M/Fü
—
Complete wall breakthrough (see Fig. 10 on page 20) for installation kit
with
filler piece M-WRG-II M/Fü
8.3
Chasing out channels for flat ductwork or flexible pipes
NOTICE
With this installation kit you can connect to the extract air and supply air openings using
either flat ductwork or flexible pipe. Various sample configurations are illustrated below.
8.3.1
Chasing out channels for two flat ductwork connections (single room
version)
►
Use the wall chaser to chase out
two channels 125 mm wide, 85 mm
deep and at least 210 mm high (see
Fig. 11) for both the extract air duct
(item 1 in Fig. 11) and the supply air
duct (item 2 in Fig. 11).
► Check that the installation kit fits
easily into the wall breakthrough.
►
Check that the installation kit can
be pushed far enough into the wall
breakthrough for the front surface to
end flush against the solid wall; the
plastering trim must protrude 15 mm
beyond the solid wall.
►
If necessary, use the wall chaser to
chase out channels for the rest of the
flat ductwork as shown in your plans.
Fig. 12 and Fig. 13 on page 22 show
examples with the flat ductwork running
vertically and horizontally.
NOTICE
The dimensions of the wall channels for the flat ducts are:
— 125 mm wide
— 85 mm deep
Fig. 11:
Chasing out channels for flat ductwork
connections, dimensions in millimetres
228
min. 210
85
125
228
104
104
1
2