* All installations in England and Wales must be notifi ed to Local Authority Building Control (LABC) either directly or through a Competent Persons Scheme.
A Building Regulations Compliance Certifi cate will then be issued to the customer.
© Heating and Hotwater Industry Council (HHIC)
www.centralheating.co.uk
SOLAR THERMAL COMMISSIONING CHECKLIST
This Commissioning Checklist is to be completed in full by the competent person who commissioned the Solar Thermal System and associated equipment
as a means of demonstrating compliance with the appropriate Building Regulations and then handed to the customer to keep for future reference.
Failure to install and commission this equipment to the manufacturer’s instructions may invalidate the warranty but does not affect statutory rights.
Customer Name
Telephone Number
Address
Commissioned by
(print name)
Company Name
Telephone Number
Company Address
Commissioning Date
To be completed by the customer on receipt of a Building Regulations Compliance Certifi cate.
Building Regulations Notifi cation Number (if applicable)
Confi rmation that required areas of the installation have been notifi ed to Local Authority Building Control (LABC)
a). Initials of commissioning engineer
b). Competent Persons Scheme (CPS) details or details of LABC direct notiifi cation
Confi rmation that panels have been installed without lessening the structure, weathering and fi re resistance of the roof in accordance with the
relevant Building Regulations and standards. Initials of commissioning engineer
COLLECTOR DETAILS
Make of collector
Model of collector
Serial number of each collector:
(if more than 6 collectors please append additional sheet)
i.
ii.
iii.
Iv.
v.
vi.
INSTALLATION DETAILS
Solar System Operating Pressure bar (cold)
Expansion vessel air/nitrogen charge bar (cold)
Expansion or drain back vessel size litres
Operating correctly: Yes Treated for leaks and fl ushed: Yes
Filled and purged for air: Yes
System heat transfer fl uid details:
What type/make of heat transfer fl uid used?
System volume litres
What is the fl uid mix: Water %
Glycol %
Frost protection provided to °C
Is the installation in a hard water area (above 200ppm)?
Yes
No
If yes, has a water scale reducer been fi tted or has Tmax been limited to 60˚C?
Yes No
What type of scale reducer has been fi tted?
Air purged from solar primary circuit: Yes Primary circuit valves and air vent(s) set to fi nal operating positions:
Yes
Pump speed setting recorded: Speed setting Max fl ow rate litres/min
Solar primary circuit pressure relief valves tested for correct operation: Yes Location
Device for limiting hot water temperature outlets has been fi tted:
Yes
No
Type
Location
All exposed pipework lagged in accordance with regulations using suitably temperature rated materials
Yes
For unvented hot water storage cylinder, will controls stop solar fl uid circulation in the event of cylinder overheating?
Yes
SOLAR SYSTEM CONTROLS
Make and model of DTC
Temperature sensors checked and operating correctly
Yes
Differential Temperature Controller (DTC) settings: T on °C T off °C
T max °C Other DTC Settings
Thermostat located in back-up heating zone of cylinder
Yes
No
Have optimum settings for HW controls been explained to the customer?
Yes
No
Does this include Legionella Bacteria protection settings with back up heating system to bring boiler volume to 60°C for an hour once a day?
Yes
No
Electrical installation is accordance with BS7671
Yes
Location of electrical isolation switch to solar control/pump unit
ALL INSTALLATIONS
The heating and hot water system complies with the appropriate Building Regulations
Yes
The system and associated products have been installed and commissioned in accordance with the manufacturer’s instructions
Yes
The effi cient operation of system and its controls have been demonstrated to and understood by the customer
Yes
The manufacturer’s literature, including Benchmark Checklist and Service Record, has been explained and left with the customer Yes
Commissioning Engineer’s Signature
Customer’s Signature
To confi rm satisfactory demonstration and receipt of manufacturer’s literature)
Summary of Contents for Eco SolaReady
Page 1: ...Hot Water Cylinders MEGAFLO Eco SolaReady Unvented MEGAFLO Eco SolaReady Product Guide...
Page 48: ...SERVICING 48...
Page 50: ...SERVICING 50...
Page 51: ...SERVICING 51 Notes...