Basic Connections

 

AGDS-2em 

230v Supply 

3Amp Fused Spur 

EM Stop  Buttons, 

Thermal links  

(Normally closed) 

 

For multiple, connect in 

series.  

Gas Solenoid 

Earth Connections not shown 

Gas detector 

Set to address 1 

Enable channel 1 

(

12

Mains Rated  

Potential free contact,  

Max  load 5amp’s 

(latching relay) 

Gas detector 

Set to address 2 

Enable channel 2 

(

12

    Wiring information 

All current wiring regulations must be followed with reference to running low and mains voltage cables together. 
 
The maximum cable length between a detector and the control panel should not exceed 100 metres, if the distance between 
the main panel and the detectors is greater than 20metres a 1mm screened cable must be used on the +VE, 0v terminals 

 

Gas detectors, require a four core screened Belden type security cable or 600v rated BMS cable (max cable length of 
100meters.)  
Remote emergency stops and thermal links require a two core screened cable. 
Warranty will be void if Fire Protection Cable or cable over 1mm dia. is used on the SELV side. 

Summary of Contents for AGDS-2em

Page 1: ...talled and commissioned to the satisfaction of the manufacturer A commissioning certificate must be issued to the end user along with instructions for the operation of the equipment As the Manufacture...

Page 2: ...the High alarm Carbon Monoxide detectors are pre calibrated at 80ppm pre alarm and 100ppm for high alarm Connect a detector to either the detector 1 terminals 6 7 or detector 2 terminals 8 9 each det...

Page 3: ...connection Reset 12 Enable Detectors Channels enable a channel when it has a detector connected 13 High alarm time delay function Controls the length of time between a High alarm and the closing of t...

Page 4: ...t be followed with reference to running low and mains voltage cables together The maximum cable length between a detector and the control panel should not exceed 100 metres if the distance between the...

Page 5: ...hould be wired in series with the EM stop buttons To EM Stop connections in the panel Indicator bar shows when pressed Normal EM Stop Activated Multiple Stop Buttons Single Stop Buttons Resetting indi...

Page 6: ...that is being monitored for See the gas detectors own instructions for more guidance All current wiring regulations must be followed with reference to running low and mains voltage cables together Th...

Page 7: ...g head height and between 1m and 3m from the potential source Care should be taken so they are not located close to the edge of a canopy or in direct flow of the supply or extract ventilation For addi...

Page 8: ...plier Medem UK will exchange faulty valves for return to the manufacturer 5 Where a Medem UK engineer or another company appointed by Medem UK commission and installed system then that system will car...

Page 9: ...ctor 1 or detector 2 on the panel 5 Enable the detector channels 1 or 2 as being used by with switch 12 Connect the 3 amp fused spur 240 volt supply to marked terminals 6 Once power is connected to th...