16
Responsibility
The responsibility for assuring that this procedure is followed is binding upon all employees and
service personnel from outside service companies (Installers, contactors, service repairmen). All
employees shall be instructed in the safety significance of the lockout procedure by the facility
owner/manager. Each new or transferred employee along with visiting outside service personnel
shall be instructed by the owner/manager (or assigned designee) in the purpose and use of the
lockout procedure
Preparation
Employees authorized to perform lockout shall ensure that the appropriate energy isolating device
(circuit breaker, fuse, disconnect, etc.) is identified for the lift being locked out Other such devices for
other equipment may be located in close proximity of the appropriate energy isolating device. If the
identity of the device is in question, see the shop supervisor for resolution. Assure that proper
authorization is received prior to performing the lockout procedure.
Sequence of Lockout Procedure
Notify all affected employees that a lockout is being performed and the reason for it.
Unload the subject lift. Shut it down and assure the disconnect switch is "OFF" if one is provided on
the lift.
The authorized lockout person operates the main energy isolation device removing power to the
subject lift.
If this is a lockable device, the authorized lockout person places the assigned padlock on the device
to prevent its unintentional reactivation. An appropriate tag is applied stating the person's name, at
least 3"x 6" in size, an easily noticeably color, and states do not operate device or remove tag.
If this device is a non-lockable circuit breaker or fuse, replace with a "dummy" device and tag it
appropriately as mentioned
above.
Attempt to operate lift to assure the lockout is working. Be sure to return any switches to the "OFF"
position.
The equipment is now locked out and ready for the required maintenance or service.
Restoring Equipment to Service
Assure the work on the lift is complete and the area is clear of tools, vehicles, and personnel.
At this point, the authorized person can remove the lock (or dummy circuit breaker or fuse) & tag and
activate the energy isolating device so that the lift may again be placed into operation.