Malvern tentwenty Installation & Service Instructions Manual Download Page 9

Condensing Boiler

     

8

           22/10/02

minimum of 19mm pipe. External runs MUST be
made in a minimum of 32mm pipe, starting inside
the building, and if possible insulated to defer
problems from freezing.

Whichever method is used it should be checked
during commissioning to prove there is a leakfree
working connection from the boiler to the drain. The
simplest way to do this is to carefully pour some
water into the boiler flue and check it emerges at the
drain.

The British Gas booklet “Guidance for the installa-
tion of Domestic Condensing Boilers” should also be
referred to.

System Design

General principals

The system should be designed to conform with
the latest reuirements of the Building Regula-
tions.
Condensing Boilers give their best performance
when the system water temperature is as low as
possible and still achieve the desired room tempera-
tures. Oversized radiators make this easier to
achieve but are not essential as, even in a standard
designed installation, most of the boilers’ working
hours are spent with the system producing much
less than the designed output. This is because the
outside temperature is often higher than the figure
used for the design, typically -1 to -2º C.

A design using 3-port flow-share valve, room ther-
mostat and cylinder thermostat, is a perfectly
suitable minimum. The boilers include a pump
overrun device so it is essential that there is an
open circuit for water to flow between the flow and
return. In some system designs this may require the
addition of a bypass, an automatic bypass is pre-
ferred.

They also contain integral frost protection, the boiler
will fire if the temperature within it approaches
freezing. It will do this even when turned to Off, and
can only be inhibited by removing the Permanent
Live supply to the boiler.

Thermostatic radiator valves can be used but it is
essential to fit a bypass to maintain minimum flow
conditions. An automatic bypass is preferred.

The boiler waterside is completely copper so all
good corrosion inhibitors are suitable.

Designs

The following designs are all acceptable:

1. Sealed system to BS.6798 and BS.5449:1

2. Combined Feed and Vent systems.

3. Separate Cold Feed and Vent systems.
The pump may be on the flow or return, but careful
note of its position relative to the feed and vent
MUST be made to avoid pumping over, or sucking
in air. It should always be installed with isolating
valves as close as possible on both its flow and
return. The design temperature difference across
the boiler for optimum operating efficiency is 20ºC. If
thermostatic valves or zone valves are used ensure
the minimum flow shown in the Technical Data on
page 1
 is possible.

Electrical Connections

WARNING: The appliance MUST be earthed.

All wiring for the boiler and system controls MUST
conform to I.E.E. Wiring Regulations, and work
should be tested using a suitable meter, for Earth
Continuity, Polarity, Short Circuit and Resistance to
Earth.

The supply must be through a common isolator, a
double pole 3A fused isolating switch with a contact
separation of 3mm minimum on both poles. The
cable used should be no less than 0.75mm

2

  to

BS.6500 PVC, 3 core, and fixed ensuring the earth
connection is longer than the Live and Neutral.

Access to the boiler connections is made by with-
drawing the Electrical Tray then releasing the single
screw retaining the cover over the push fit screw
terminals. The boiler internal wiring is shown in
Fig.3 and Fig.4.

Connections are as follows :-

4 Way Terminal

Supply Connection

Earth

N

Mains Neutral

Ls

Switched Live

L

Permanent Live

3 Way Terminal

Pump Connection

Earth

N

Pump Neutral

L

Pump Live

The boiler includes a pump overrun and an external
pump MUST be powered from the Pump push-fit
connector.
For systems using an external programmer, the
electrical wiring should follow the relevant control
manufacturer’s recommendations, with the switched
live from the controls returning to Ls in the 4 way
push-fit connector.

Summary of Contents for tentwenty

Page 1: ...1 555 18 41 555 19 Serial Number 0087 tentwenty twentytwentysix Condensing Boilers Installation Service Instructions Note to the Installer Natural and Propane Gas Please leave these Instructions adjac...

Page 2: ...P 20 kg 28 kg 1 4 litres 3 bar 1 m 30 82 C 10 12 litres m 5 litres m 22mm Copper 230V 50Hz 40W 1 Amp 20mm 3 Amp 790 High 400 Wide 330 Deep 450 Front 30 Above 25 Below 30 Left Right Concentric 160 High...

Page 3: ...s may require the addition of a bypass an automatic bypass is preferred The boilers also contain integral frost protection the boiler will fire if the temperature within it approaches 4 to 5 degrees C...

Page 4: ...he purpose Details of essential features of cupboard compartment design including airing cupboard installations are given in BS 6798 In siting the boiler the following limitations MUST be observed 1 T...

Page 5: ...ter system if applicable should be in accordance with the relevant recommenda tions of BS 5546 Copper tubing to BS 2871 1 is recommended for water carrying pipework The hot water storage cylinder MUST...

Page 6: ...The boiler is supplied for 230V 50Hz Single phase Fuse rating is 3A The method of connection to the mains electricity supply MUST facilitate complete electrical isolation of the boiler preferably by t...

Page 7: ...cut off during installation Right or Left Outlet 1 Secure the 50mm flue tube with ELBOW connec tor on the saddle using the Velcro strap See Fig 7 2 Measure carefully and saw off the 50mm tube to give...

Page 8: ...and Side Trim 3 With the bottom of the boiler away from the wall hang the top of the back panel onto the Mounting Box Now by gently lowering the bottom of the boiler against the wall the fan spigot sh...

Page 9: ...minimum flow conditions An automatic bypass is preferred The boiler waterside is completely copper so all good corrosion inhibitors are suitable Designs The following designs are all acceptable 1 Seal...

Page 10: ...pletely normal It is recommended that the gas cock is turned off during this early stage Because of a built in delay the boiler is always held off for a minimum of 120 seconds However for commissionin...

Page 11: ...em hot check again for water sound ness Refit the case to the boiler Add remainder of corrosion inhibitor Balance the system in the normal way to obtain even heating of all radiators If fitted set the...

Page 12: ...fill system adding 3 4 of the inhibitor Do not light boiler Vent all radiator and air release points Run pump for 5 10 second bursts and revent Condensing Boiler 11 06 06 01 Do not light boiler Run pu...

Page 13: ...ngths Minimum 200mm Maximum 22m horizontal 90mm 90 bend 4 0m 45 bend 1 3m Suggested core drill Suggested core drill 128mm Flue 100 to 2000mm Left right or rear Flue Air Concentric Flues Service Access...

Page 14: ...NSOR 12 Way connector GV1 GV2 N 4 Core to Gas Valve Fan 4 way Molex 10 way Molex GV1 GV2 1 Amp 20mm CONTROL BOARD Or Or Br Br R W Bk Gy Br R Bk Br G G Y G Y G Y B G Y V Gy Br R Or W Bk Gy V G Y B Brow...

Page 15: ...Condensing Boiler 14 06 06 01 Physical Wiring Diagram Fig 4...

Page 16: ...Wall Fixing Holes 2 Lower Wall Fixing Holes Core Drill 128mm 118 Use 2 at the top and any other 2 below 236 288 167 92 32 17 kW For Concentric 270 For Twin Pipe Core Drill 90 mm Condensing Boiler 15...

Page 17: ...1 Boiler Panel Assembly Control Board Chassis Electrical Cover Top Trim Front Burner Baffle Side Trim Fig 6 Pressure Cover Concentric Flue Boiler Mounting Box Fan Protection Hoop Lower Burner Baffle T...

Page 18: ...e Positions Fig 7 Fig 8 Flue Duct Air Duct 100mm Condensate Drain Connection connects to drain point on Flue Spigot Adapter Flue Spigot Adapter Drain Point Twin Pipe Boiler Mounting Box Assembly Conne...

Page 19: ...me is detected and the control board stops sparking and then energises the main gas valve and the burner lamp is illuminated The pilot flame lights the burner and it stays alight until turned off by t...

Page 20: ...Condensing Boiler 19 03 07 03 Fault Diagnosis...

Page 21: ...quired If in doubt drain the system and remove for inspection 2 Condensate Syphon With a suitable bowl to catch the water un screw the drain cap s on the underside of the Syphon trap and drain the wat...

Page 22: ...NCE CASE COULD RESULT IN LEAKAGE OF COMBUSTION PRODUCTS INTO THE ROOM 3 Fan Assembly Lower the Electrical Tray Remove the Case Undo the wing nut holding the Fan Protec tion Hoop Pull the electrical co...

Page 23: ...ove the Case Pull off the HT lead from the Control board Undo the left and right screws holding the Front Burner Baffle Remove the front baffle Release the tube nut holding the electrode to the Pilot...

Page 24: ...04 Fan Assembly 17 kW M1095 Fan Assembly 24 kW M0910 106 435 Control Board M3752 Control Assembly M3915 Gas Valve Sigma 840 M3783 Air Pressure Switch Concentric Flues 7712 379 091 Air Pressure Switch...

Page 25: ...ces Flue Thermostat Fan Assembly Secondary Heat Exchanger Fibre Washer 2 Places Flow Pipe Control Sensor O H Stat Primary Heat Exchanger Gas Manifold HT Lead Pilot Assembly Main Injector Electrode Pil...

Page 26: ...Trap Air Gap Air Gap 110mm Soil Pipe or Drain Soakaway Insulate against freezing 150mm Land Drain Filled with Gravel 750mm deep Condensate Drain from Boiler Air Pressure Switch pipe connection Vent Sy...

Page 27: ...e specification without notice Your statutory rights are not affected Malvern Boilers Ltd Enigma Business Park Spring Lane Malvern WORCS WR14 1BW Telephone 01684 893777 Fax 01684 893776 www malvernboi...

Reviews: