Air regulator installation and operation
1.
Firmly tight and seal the copper air hole at IN and OUT terminal by high pressure
rubber tube firmly .
2.
Tight and seal the meter with meter face rubber tube.
3.
Fix the connecting shelf with screw as the regulator position.
4.
Get down the plastic screw and fix the regulator on the shelf.
5.
Turn on the air valve, turn up the pressure adjusting knob, Turn the pressure to
rated volume(meter inside shows KG), and then put down the knob.(+ means
increasing pressure, -- means decreasing pressure.)
6.
Scale of the meter is as follow. The volume in the picture is 6 kg.
7.
If the water in the gas filtering bottle is too much, please turn on the water valve
to let the water go out.
Regulator installation
INSTALLATION