WIRING INSTRUCTIONS

 

SCREW TERMINAL 

 

Torque

: 0.8 N·m

CHECKING

  1 ) Terminal wiring:  Check that all cables are correctly 

connected according to the connection diagram.

  2 ) Auxiliary power input voltage:  Check voltage across 

terminal 9 – 10 with a multimeter.

  3 ) Input:  Check that the input shows within 0 – 120% of 

the rated voltage.

  4 ) Output:  Check that the load resistance meets the de-

scribed specifications.

ADJUSTMENT PROCEDURE

This unit is calibrated at the factory to meet the ordered 
specifications, therefore you usually do not need any cali-
bration.
For matching the signal to a receiving instrument or in case 
of regular calibration, adjust the output as explained in the 
following.

 

HOW TO CALIBRATE THE OUTPUT SIGNAL

Use a signal source and measuring instruments of suffi-
cient accuracy level.  Turn the auxiliary power supply on 
and warm up for more than 10 minutes.

  1 ) ZERO:  Apply 0% input and adjust output to 0%.
  2 ) SPAN:  Apply 100% input and adjust output to 100%.
  3 ) Check ZERO adjustment again with 0% input.
  4 ) When ZERO value is changed, repeat the above proce-

dure 1) – 3).

  5 ) Go through the above procedure for channels 2 and 3.

MAINTENANCE

Regular calibration procedure is explained below:

 

CALIBRATION

Warm up the unit for at least 10 minutes.  Apply 0%, 25%, 
50%, 75% and 100% input signal.  Check that the output 
signal for the respective input signal remains within accu-
racy described in the data sheet.  When the output is out of 
tolerance, recalibrate the unit according to the “ADJUST-
MENT PROCEDURE” explained earlier.

LIGHTNING SURGE PROTECTION

M-System offers a series of lightning surge protector for 
protection against induced lightning surges.  Please contact 
M-System to choose appropriate models.