45-0101 - Rev 2.0
2
Electrical Installation - 2 Wire Option
www.Lumishore.com
Lumishore UK Unit 2, Technium 1, Kings Road, Swansea, SA1 8PH, UK | +44(0)208 144 1694 | [email protected]
Electrical Installation - SUPRA i-Connect Hub
The light cables can be extended. Ensure the correct cable gauge is
used to avoid issues with voltage drop. Follow ABYC recommenda-
tions for no more than 3% voltage drop at 12V, and 10% at 24V.
Consult a qualifed electrical installer, or contact Lumishore for further
information.
Make sure the lights are tested, and working as expected before the
boat goes back in the water.
Battery / PSU (12 or 24V DC)
Red
(+VDC)
Red
(+VDC)
Black
(GND)
Fuse
Fuse
Switch
Off
On
Fuse or
Circuit
Breaker
The lights operate in White, Blue, Random Strobe, and Colour Fade
modes. To change the mode turn the switch OFF / ON (wait a
second before switching back on). To reset to White, switch the
lights off for 5 seconds. The lights will always come on in White
mode when first switched on.
Plan the cable route prior to instalation. Ensure all cables are suitable
for marine applications, and correctly rated for the required voltage
and current. Each light must be
individually fused
. The cable connec-
tions are:
Red
12V or 24 V DC
Black
Ground
The fuse ratings are:
12 V DC
7.5A
24
V
DC
4A
An ON / OFF switch should be installed to select the modes of opera-
tion.
All connections must be made waterproof.
Note: This option requires a Lumishore SUPRA i-Connect Hub
(60-0317) and SUPRA SUPRA i-Connect Hub Switch (60-0318). The
SUPRA i-Connect Hub is Lumi-Link compatible which allows control
via certified MFD or iOS connected device - see datasheet for further
details.
Plan the installation first. Work out where the lights will be mounted.
Each light connects to the hub using a field installable connector
(supplied). One hub can power up to 4 lights, and 2 hubs can be
connected together in one system. The hub should be mounted
between the lights and the power source. Plan the cable routes,
including the switch, prior to installation. Ensure all cables are marine
Note: Two hubs can be connected together. All they need is power
connected, and a pre-moulded data cable run between the hubs (see
connecting multiple hubs section for wiring diagram).
The light and power cables can be extended. Ensure the correct cable
gauge is used to avoid issues with voltage drop. Follow ABYC recom-
mendations for no more than 3% voltage drop for 12V, and 10%
voltage drop for 24 V. Consult a qualifed electrical installer, or contact
Lumishore for further information.
Installing the hub(s):
1. Select a site for the installation of the SUPRA i-Connect Hub(s). This
should be within reach of the light cables that will be attached to the
hub(s). The hub(s) should be in a dry, well ventilated area. The hub(s)
should NOT be mounted in areas prone to flooding or excess heat.
2. The hub(s) should be mounted to a flat surface, with room for
access to the fuse panel and connectors.
3. Mount the hub(s) as close to the power source as possible. Run the
power cable to the hub(s) from the power source.
Use correct cable gauge -
consult ABYC recomendations
for MAX 3% voltage drop at
12V, and max 10% voltage
drop at 24V.
Warranty
Battery /
PSU
12 or 24 V
SUPRA i-Connect
Hub
On/Off
Scene
SUPRA i-Connect Hub Switch
Field Installable
Connectors (Supplied)
Removable
Fuse Cover
Fuse or
Circuit
Breaker