Lucent Technologies Lineage
®
2000 ECS/GPS Battery Plant J85500G-2
Issue 6 May 1999
Installation 4 - 1
4
Installation
General
As mentioned at the beginning of Section 3, Lucent
Technologies offers complete engineering and installation
service that result in “turn-key” plant operation. Contact your
Lucent Technologies Energy Systems Account Executive for
further information on the complete range of installation
services available from Lucent. Customers may, however,
choose to make their own arrangements to fully or partially
install the battery plant based on the information supplied here.
This section outlines an efficient sequence of battery plant
installation steps that minimizes the installer’s exposure to live
circuits. Upgrades, retrofits and replacement of equipment in the
controller, rectifier and battery subsystems are covered in their
respective manuals.
The framework, rectifier, controller and dc distribution
subsystems, described in Section 2, are factory tested as a
system. The controller and distribution subsystems are shipped
assembled to the framework, ready for use. To improve shipping
and handling, the rectifiers are packaged separately and must be
plugged into their shelf assemblies during the plant installation
process. The battery subsystem must also be assembled by the
installer. The battery plant installation sequence that follows
refers to the Rectifier, Controller and Battery manuals for details
for those subsystems. Read this section and the referenced
sections in other subsystem manuals completely before starting
any work.
Installation tools
and test
equipment
The following tools and test equipment are required for battery
plant installation and testing.