Lucent Technologies Lineage
®
2000 ECS Battery Plant H569-403
4 - 6 Installation
Issue 4 February 1997
Battery Stand
Assembly
Assemble battery stands or shelves as instructed in the battery
manufacturer's documentation. Install the batteries onto their
stands or into their shelves.
Initial Charge
Batteries may undergo initial charging at this time, according to
the manufacturer's recommendations. One of the rectifiers may
be used for initial charging. Refer to the procedure given in the
Rectifier manual.
Cable Support
and Ground
System
Hang all cable support systems, as well as any auxiliary ground
bus bars, as dictated by the job application drawings.
Figure 4-2: Floor Mounting Template (All Dimensions Are Given in Inches)
Warning
Do not connect batteries to the system at this time.