If the system is powered by power grid, there is a presence of potentially dangerous voltage inside the box; 
the mains voltage is connected to the circuit breaker; this can be deactivated to remove the presence of 
mains voltage in places other than the switch itself; however, consider that the high voltage is generated 
during the measurements even if only the battery voltage is available. If you want to shut down the system 
completely use the switch located on the top of the 

PWR

 unit. 

The electrical cables that bring the connections back to the measuring electrodes also carry currents with 
potentially dangerous voltages. LSI LASTEM has carefully considered the safety conditions for those working 
with 

GReTA-ONE

, in particular the situation in which a subject could come into contact with the measuring 

electrodes. In this regard, the following should be considered: 

 

Each individual electrode  is powered by the  system only  for short instants and quite  rarely (alto-
gether a few seconds in each measurement session; typically, there is only one scheduled measure-
ment session each day). 

The electrocution can occur by holding in the hands two electrodes that at a given moment are activated by 
the system to perform the measurement in the ground right at the position of the subject. It should be con-
sidered that the typical duration of the injection is about 300 ms x 2 (twice because for each measurement 
the injection is considered in the opposite direction and then in the direct direction for the depolarization of 
the soil) and 1000 ms x 2 at the most, therefore still insufficient to cause death. Considering a condition highly 
unlikely to occur, but not theoretically impossible, in which the operator is in contact with two electrodes, 
the instrument is performing a measurement precisely on those elements and, fatally, just at that moment a 
block to the automatic signal switching system occurs, in this case there would be a permanent presence of 
the voltage to the electrodes in contact with the subject; in this situation there is a circuit specifically provided 

in the instrument that can detect the system’s block condition and therefore authoritative in the deactivation 

command of the entire high voltage supply system. This circuit, in order to ensure maximum operating con-
ditions and reliability, works with dedicated hardware and is completely independent from the other parts 
of the injection and measurement system managed by the logical units of the instrument. 
 

1.3

 

Pre-installation requirements 

1.3.1

 

Power connection 

Whenever available at the installation site, the G.Re.T.A. system should preferably be connected directly to 
the electrical grid. For this purpose, a 230 Vac power line should be laid in order to reach the plinth and have 
sufficient spare cable to reach the G.Re.T.

A. box located approximately at 1 m height from the soil’s surface.

 

If the electric grid is not available at the installation site, the system may be powered by a solar panel placed 
on top of the pole.  
 

1.3.2

 

Internet connection 

The G.Re.T.A. system communicates via Internet connection. The system comes with a 3G/4G modem/router 
however without a SIM card, which must be provided locally by the user. Make sure to make available a 
3G/4G SIM card at the day of installation and to have tested the coverage of the related telephone operator 
at the installation site beforehand. 

Summary of Contents for GRETA

Page 1: ...Environmental monitoring solutions Installation manual...

Page 2: ...he information included in this manual is subject to changes without notice No part of this manual may be reproduced in any form or by any electronic or mechanical means for any use without LSI LASTEM...

Page 3: ...requirements 5 1 3 1 Power connection 5 1 3 2 Internet connection 5 2 Installation 6 2 1 Plinth installation 6 2 2 Excavation of the trench 6 2 3 Unwind of the cable 7 2 4 Screw the electrodes 7 2 5 M...

Page 4: ...e any operation on electrical connections power sensors and communication equipment Turn off the power Discharge the accumulated electrostatic charges by touching a conductor or a grounded system Do n...

Page 5: ...most therefore still insufficient to cause death Considering a condition highly unlikely to occur but not theoretically impossible in which the operator is in contact with two electrodes the instrumen...

Page 6: ...orted by a galvanized iron tripod which has to be placed and fixed on a concrete plinth preferred or buried in the soil The plinth has to be placed in correspondence of the centre of the trench If the...

Page 7: ...the profile where the plinth is installed The first electrode must be positioned in correspondence of the m 0 of the trench 2 4 Screw the electrodes The electrodes are provided separately from the ca...

Page 8: ...rench and bury the electrodes When the trench is buried insert the cables inside the trench taking care of the distance of the central electrodes last electrode of first cable and first electrode of s...

Page 9: ...not pour water or salty water on the electrodes press them and cover them with more soil or use bentonite to enhance the contact Re do the contact resistance test 2 8 Cover the trench Mark the positi...

Page 10: ...GReTA Installation manual LSI LASTEM SRL INSTUM_04546_en Pag 10 10...