Lochinvar Crest FBL0751 Installation & Operation Manual Download Page 53

53

        

Installation & Operation Manual

General

How the boiler operates

The Crest uses an advanced stainless steel heat exchanger 
and electronic control module that allows fully condensing 
operation.  The blower pulls in air and pushes flue products 
out of the boiler through the heat exchanger and flue piping.  
The control module regulates blower speed to control the 
boiler firing rate.  The gas valves sense the amount of air 
flowing into the boiler and allow only the right amount of 
gas to flow.

How the control modules operate

The Crest boiler is equipped with a SMART TOUCH control 
module.  The SMART TOUCH control module receives 
inputs from boiler sensors and external devices.  The control 
module activates and controls the blower and gas valves 
to regulate heat input and switches the boiler, Hot Water 
Generator (HW), and system pumps on and off as needed.  
The user programs the control module to meet system needs 
by adjusting control parameters.  These parameters set 
operating temperatures and boiler operating modes.  

Control inputs and outputs

Enable

This input tells the boiler to provide water for space heating.

Hot Water Generator (HW) tank thermostat

This input tells the boiler to provide water for heating an 
indirect HW tank.

0 - 10V BMS input (set point or power)

The Crest can be controlled by a Building Management 
System (BMS) using a 0 - 10 VDC signal.  The control can be 
configured by the installer to use this signal to either control 
set point or firing rate.

0 - 10V System Pump speed input

When a variable speed system pump is used, and there is a 
0 - 10V signal available from the pump speed control, this 
signal may be connected to the boiler.  Doing so will allow 
the boiler to anticipate changes in the BTU’s needed by the 
system as the system flow changes, and therefore, help the 
boiler to maintain the desired system temperature.  Connect 
the - input terminal to the COM or - output terminal on the 
pump speed control, and the + input terminal to the 0 - 10V 
or + output terminal on the pump speed control.  Note that 
the voltage on these inputs must never go below ground.

HW priority

The SMART TOUCH control allows the connection of a HW 
thermostat or tank sensor to the low voltage connection board.  
When a tank sensor is connected, the HW thermostat input is 
ignored.  When a boiler is programmed for HW Normal Mode, 
the maximum firing rate can be limited to match the input 
rating of the indirect tank coil.

HW / space heating (SH) cycling

If a HW call for heat is received while a space heating call is in 
progress, and the HW is in Normal Mode, the control will start 
the HW pump and shut the boiler pump off. The system pump 
will remain on. For stand-alone boilers, if the space heating call 
is still active while the HW call is in operation, the control will 
wait for 30 minutes (time adjustable by installer) then it will 
switch back to the space heating demand. There is a timer to 
switch from space heating to HW and a timer to switch from 
HW to space heating. The control will switch back and forth 
until one of the heat demands end. This function does not apply 
to cascade systems.

Controlling sensor

The control module is programmed to use the outlet sensor 
as the control sensor by default.  If a system supply sensor 
is connected, the control automatically uses it as the control 
sensor. The control module may be programmed to use the inlet 
sensor as the control sensor instead.  In this case, the control 
will use the system return sensor if it is connected.

Anti-cycling

After a space heating demand has been satisfied, the control will 
delay the next space heating call for a set time period (time is 
adjustable by the installer).  The time delay will be bypassed if 
the inlet water temperature drops too far during the delay.

Boiler, system, and HW pump control

When a space heating call for heat starts and no HW call is on, 
the boiler pump is turned on.  The system pump will turn on 
also if it is programmed to do so.  If a HW call for heat is on, the 
boiler pump will wait to turn on until just before the HW pump 
turns off.  After the space heating call for heat ends, the boiler 
pump will run for an additional period of time.

When a HW call for heat starts, the HW pump is turned on.  If 
a space heating call for heat is on, the boiler pump will turn off 
a few seconds after the HW pump turns on.

Louver

When the boiler needs to control combustion air louvers, 
connect a 24 VAC louver relay to the two (2) Louver Relay 
terminals.  Connect the Louver End Switch to the Louver 
Proving Switch input on the Low Voltage Connection Board.

Temperature control

Modulation

The Crest is capable of modulating its firing rate from a 
minimum of 4-6% (depending on model) to a maximum of 
100%.  The firing rate is dictated by the call for heat (i.e., space 
heating or hot water generation), the heating load, ramp delay 
(if enabled), and various other temperature limitations.

10  

Operating information 

 

Summary of Contents for Crest FBL0751

Page 1: ...this manual and the Crest Service Manual before installing Perform steps in the order given Failure to comply could result in severe personal injury death or substantial property damage WARNING Save t...

Page 2: ...l Vent 14 Direct Venting Options Vertical Vent 14 Direct Venting Options Vert Vent Opt Rm Air 14 Direct Venting Options Vert Vent Sidewall Air 14 Install Vent and Combustion Air Piping 15 Air Inlet Pi...

Page 3: ...ic and can attack gaskets and seals used in hydronic systems When calling or writing about the boiler Please have the boiler model and serial number from the boiler rating plate Consider piping and in...

Page 4: ...s are used to monitor the outlet water temperature if either device senses the water temperature exceeding the predetermined setting the boiler will shut down 20 Ignition electrode An electrical spark...

Page 5: ...t works continued 5 Installation Operation Manual IMG01025 2 39 1 11 Front View IMG01128 36 7 19 12 29 20 6 5 35 3 18 Rear View IMG01130 33 17 16 34 37 9 41 IMG01129 25 26 21 22 15 4 30 31 28 14 32 10...

Page 6: ...are based on net installed radiation of sufficient quantity for the requirements of the building and nothing need be added for normal piping and pickup Ratings are based on a piping and pickup allowan...

Page 7: ...flammable liquids This appliance requires a special venting system Use only the vent materials specified in this manual Failure to follow all instructions can result in flue gas spillage and carbon m...

Page 8: ...You may use any of the vent air piping methods covered in this manual Do not attempt to install the Crest using any other means Be sure to locate the boiler such that the vent and air piping can be r...

Page 9: ...pliance see Section 2 General Venting Table 2A 1 For stainless steel venting an adapter of the same manufacturer Table 2B may be used at the flue collar connection Size To ensure proper pipe size is i...

Page 10: ...st fan Close fireplace dampers DANGER WARNING At the time of removal of an existing boiler the following steps shall be followed with each appliance remaining connected to the common venting system pl...

Page 11: ...d at least half way under the boiler heat exchanger to assure proper lifting technique with no damage to the boiler d If lifting by crane is desired remove the top access panels to gain access to the...

Page 12: ...truction 3 A combination of indoor and outdoor combustion air may be utilized by applying a ratio of available volume to required volume times the required outdoor air opening s size s This must be do...

Page 13: ...ve requirements are for the appliance only additional gas fired appliances in the equipment room will require an increase in the net free area and or volume to supply adequate combustion air for all a...

Page 14: ...14 Installation Operation Manual Vertical IMG01033 2 General venting IMG01059 IMG01056 Sidewall Direct venting Vertical Vent Sidewall Air Sidewall IMG01057 Vertical IMG01058 Optional room air...

Page 15: ...s instructions can result in personal injury death or property damage Mixing of venting materials will void the warranty and certification of the appliance NOTICE The use of double wall vent or insula...

Page 16: ...erly seal all joints and seams as required in the air inlet piping may result in flue gas recirculation spillage of flue products and carbon monoxide emissions causing severe personal injury or death...

Page 17: ...dapters Category IV Model ProTech Z Flex Heat Fab Adapter Intake Adapter Intake Adapter Flue Intake 751 1001 810003974 810003269 2SVDSA06 2SVEE0690 9601MAD CCK06TM 9690 9692 1251 810003980 810003281 2...

Page 18: ...ial of severe personal injury or death check for areas and products listed in Table 1A page 9 before installing the boiler or air inlet piping If contaminants are found you MUST Remove products perman...

Page 19: ...1751 8 100141561 FB2001 8 100141561 NOTICE When Crest boilers are common vented hot water generators MUST BE piped to the primary heating loop and tank thermostats must not be connected to the Crest I...

Page 20: ...M D2466 PVC Schedule 80 ANSI ASTM D2467 CPVC Schedule 80 ANSI ASTM F439 Pipe Cement Primer PVC ANSI ASTM D2564 CPVC ANSI ASTM F493 NOTICE DO NOT USE CELLULAR FOAM CORE PIPE NOTE In Canada CPVC and PVC...

Page 21: ...r substantial property damage WARNING Installations must comply with applicable national state and local codes For Canadian installation polypropylene vent must be listed as a ULC S636 approved system...

Page 22: ...local requirements and with the National Fuel Gas Code NFPA 54 ANSI Z223 1 latest edition for U S installations or CSA B149 1 Installation Code for Canadian installations WARNING NOTICE WARNING Do no...

Page 23: ...ction It is not classified as a forced air intake with regard to spacing from adjacent boiler vents 36 914 MM 36 914 MM 12 305 MM 12 305 MM 12 305 MM 12 305 MM 12 305 MM 12 305 MM Figure 3 3 Vertical...

Page 24: ...or substantial property damage Installation must comply with local requirements and with the National Fuel Gas Code NFPA 54 ANSI Z223 1 for U S installations or CSA B149 1 for Canadian installations D...

Page 25: ...CONNECTION 36 914 MM MIN 48 1219 MM MAX 12 305 MM MIN GRADE OR SNOW LINE Figure 4 2B Stainless Steel Sidewall Termination w Field Supplied Fittings 36 914 MM MIN 48 1219 MM MAX 12 305 MM MIN FROM BOIL...

Page 26: ...eration Manual 4 Sidewall direct venting continued Vent air termination sidewall 4 4 Figure 4 3 Clearance to Doors and Windows VENT TERMINATION IF LESS THAN 10 36 MIN FORCED AIR INLET AIR TERMINATION...

Page 27: ...Elbow Figure 4 6 Direct Vent Terminations ROOM AIR DIRECT EXHAUST TERMINATIONS Vent Termination 23 Elbow 45 Elbow 90 Elbow Figure 4 7 Room Air Direct Exhaust Terminations Room air IMG01036 AIR INLET C...

Page 28: ...a suitable gasket between flanges 2 Connect the system supply to the flanged connection marked Outlet make sure to install with a suitable gasket between flanges 3 Install purge and balance valve or...

Page 29: ...60 F GPM FT HD GPM FT HD GPM FT HD FB 0751 3 72 1 5 36 0 5 24 0 2 FB 1001 3 96 2 1 48 0 6 32 0 3 FB 1251 3 120 3 0 60 0 9 40 0 4 FB 1501 4 144 3 1 72 0 9 48 0 5 FB 1751 4 168 3 7 84 1 1 56 0 5 FB 200...

Page 30: ...ded when storing domestic hot water above 115 F 46 C 8 Pressure relief valve Factory supplied The pressure relief valve is sized to ASME specifications 9 System temperature sensor Lochinvar supplies a...

Page 31: ...Secondary Piping with a Hot Water Generator HOT WATER GENERATOR WATER GENERATOR CIRCULATOR BOILER PUMP FLOW CHECK VALVE TYPICAL Y STRAINER RECOMMENDED RELIEF VALVE BALL VALVE TYPICAL AIR SEPERATOR DR...

Page 32: ...SYSTEM TO SYSTEM MAKE UP WATER BOILER DRAIN TYPICAL SYSTEM RETURN SENSOR SYSTEM SUPPLY SENSOR IMG01037 Figure 5 3 Multiple Boilers Common Header Recommended Primary Secondary Flow Model Number of Unit...

Page 33: ...each system component The installer is responsible for compliance with local codes NOTICE RELIEF VALVE BALL VALVE TYPICAL AIR SEPERATOR DRAIN PORT TYPICAL SYSTEM CIRCULATOR BACK FLOW PREVENTER PRESSU...

Page 34: ...PICAL RELIEF VALVE TYPICAL AIR SEPERATOR DRAIN PORT TYPICAL SYSTEM CIRCULATOR BACK FLOW PREVENTER PRESSURE REDUCING VALVE PRESSURE GAUGE EXPANSION TANK FROM SYSTEM TO SYSTEM MAKE UP WATER BOILER DRAIN...

Page 35: ...tor to prevent debris from entering the regulator 4 Gas regulators should be installed the greater of either 20 inches or 10 pipe diameters from the nearest fitting elbow or valve to the outlet of the...

Page 36: ...NOTICE Check boiler rating plate to determine which fuel the boiler is set for Crest boilers CAN NOT be field converted Failure to comply could result in severe personal injury death or substantial p...

Page 37: ...um gas supply pressures are specified in this section of the manual 9 If gas supply pressure is within normal range and no adjustments are needed proceed on to Step 11 10 If the gas pressure is out of...

Page 38: ...ner should ignite promptly Flame pattern should be stable Turn system off and allow burner to cool then cycle burner again to ensure proper ignition and flame characteristics Gas valve replacement The...

Page 39: ...ge terminal strip in the junction box as shown in FIG 7 1 2 Provide and install a fused disconnect or service switch sized per the boiler amp draw shown on the boiler rating plate as required by the c...

Page 40: ...jumper wire between terminals 1 and 3 on connector X5 on the ModBus interface module Hot Water Generator HW thermostat 1 Connect the HW tank thermostat to the Tank Thermostat terminals on the connecti...

Page 41: ...ply sensor should be wired to the Low Voltage Connection Board at the terminals marked for the system sensor see FIG 7 3 The Leader control will use the water temperature at the system supply sensor t...

Page 42: ...YSTEM SUPPLY SYSTEM RETURN BOILER PUMP OUT OUT RATE BAS SHIELD SHIELD B A SHIELD SHIELD B A BUILDING MANAGEMENT SYSTEM TANK THERMOSTAT ENABLING DEVICE LOUVER PROVING SWITCH LOUVER RELAY AUX SWITCH 1 A...

Page 43: ...7 The neutralizer kit must be placed on a surface that is a minimum of 3 inches lower than the condensate trap with field supplied piping vacuum break installed between the condensate trap and the neu...

Page 44: ...the following for properly filling your boiler with the appropriate water chemistry for closed loop boilers Good fill water quality will help extend the life of the appliance by reducing the effects...

Page 45: ...zone Follow this procedure until all zones are purged g Close the quick fill water valve and purge valve and remove the hose Open all isolation valves Watch that system pressure rises to correct cold...

Page 46: ...e gas may no longer have an odor Before startup and periodically thereafter have the propane supplier verify the correct odorant level in the gas Check thermostat circuit s 1 Disconnect the two extern...

Page 47: ...corrects the problem refer to the Troubleshooting Section of the Crest Service Manual Check system and boiler Check water piping 1 Check system piping for leaks If found shut down the boiler and repa...

Page 48: ...an to inspect the appliance and to replace any part of the control system and any gas control which has been under water OPERATING INSTRUCTIONS 1 STOP Read the safety information above on this label 2...

Page 49: ...ing Section in the Crest Service Manual for possible causes and corrective actions Table 9A Flue Products Chart 8 Once the heater analysis is complete test the safety shutoff device by turning the man...

Page 50: ...es to be reprogrammed Set space heating operation Verify space heat circulator mode The system pump output can be programmed to never run OFF run only when a space heating demand is present ON or run...

Page 51: ...nued Set HW boiler target temperature When in the HW Mode the control will modulate to maintain the boiler outlet temperature or system supply temperature to a set point This set point is set at the f...

Page 52: ...on Access the Cascade Setup options as follows 1 Press the SETUP button on the top of the display screen 2 Enter the installer password 3 Scroll through the scrolling menu feature to access the Cascad...

Page 53: ...g rate can be limited to match the input rating of the indirect tank coil HW space heating SH cycling If a HW call for heat is received while a space heating call is in progress and the HW is in Norma...

Page 54: ...is available This output may be connected to a Building Management System BMS to allow it to monitor the actual firing rate Connect the terminal to the COM or terminal on the BMS and connect the termi...

Page 55: ...sensor is not installed Target temperature is calculated as described under Outdoor Reset Operation and Target Temperature Boost when the outdoor sensor is connected High limit operations The Crest SM...

Page 56: ...a time as possible This method will not bring on another boiler until the current number of boilers cannot meet the demand This Cascade is also required when cascading boilers in a common vent applic...

Page 57: ...to stabilize then begin modulating the firing rate in order to maintain the controlling sensor to the desired set point temperature 9 If the current call for heat is for space heating and a HW call f...

Page 58: ...basic system information It is divided into the following sections Status System Boiler Modulation and Navigation The System Section is located in the middle of the screen and displays exterior senso...

Page 59: ...ut and performance verification per Section 9 Flame inspection stable uniform Check both flame signals at least 10 microamps at high fire Clean the heat exchanger Test low water cutoff reference the C...

Page 60: ...water 1 Remove the four 4 screws securing the top cover to the condensate trap and remove the cover FIG 11 1 2 Locate the plastic ball inside the float tube Verify there is nothing under the ball cau...

Page 61: ...ust be taken to avoid contact with hot water and to avoid water damage Before operating lever check to see that a discharge line is connected to this valve directing the flow of hot water from the val...

Page 62: ...Startup of the Crest Installation and Operation Manual Do not drain the boiler unless it will be exposed to freezing temperatures If using freeze prevention fluid in system do not drain 3 Allow time...

Page 63: ...combustion chamber insulation in this appliance contains ceramic fiber material Ceramic fibers can be converted to cristobalite in very high temperature applications The International Agency for Resea...

Page 64: ...SWITCH 1 AUX SWITCH 2 ENABLE R W FLAME SENSE 1 FLAME SENSE 2 SPARK GENERATOR SPARK ROD SHIELD SHIELD A B BAS OPTION RATE OUT BOILER PUMP OUT SENSOR SENSOR TANK SENSOR OUTDOOR SENSOR BMS IN PUMP IN SH...

Page 65: ...RESET GPS1 GPS2 BR OR BLOCKED FLUE SWITCH PR BLOCKED DRAIN SWITCH BK ENABLE INLET SENSOR R W X5 BLOCK WIRING IS MODEL DEPENDENT BK T BL R W R W BR L N GND 120V ON OFF SWITCH GND GAS VALVE SMALL GAS V...

Page 66: ...Notes Installation Operation Manual 66...

Page 67: ...Notes Installation Operation Manual 67...

Page 68: ...er and 6 starter piece on page 20 R08066 along with edits made to the Gas Connections Section and the addition of the California contaminant warning on page 3 R07228 Revision D Change 500000938 reflec...