Above, all tests have been selected and have started. Electrical tests will run first.
Simple steps to have your 1200 run all the automatic tests, one right after the other:
Connect the sensors and cables from the Hub to the differential kit and the external 50ci air tank.
Verify the Hub is powered up and communicating properly by clicking on ”Hub” in the header bar to examine status.
“Trailer Information”
should be filled in as desired (
VIN number
is required). Pick the appropriate
”Configuration”
from the dropdown list available in the “Configuration” box. Select all
“Tests to Run”
by clicking on each box next to
the Test Name. Then click on
“Start”
to start running all the selected tests.
”Test Status”
may be watched on the right side of the GUI that is displayed. In the example above, the Left Taillight
test (just one of the several Electrical tests) is currently running. Many views, like this one, will only exist for a second,
flashing by on the screen. Note that the Voltage and Current of the circuit under test are being displayed in real time.
Some tests will be displaying graphs which will be updated in real time as the test progresses.
Running tests (page 1 of 3) Enter Info, select tests, start tests.
Lite-Check CERTIFIER 1200 Operations Manual