5-10
COMPONENTS
TEST PROCEDURE
RESULTS
HEATER ELEMENT
(Wire leads removed.)
MAGNETRON
THERMOSTAT
OVEN
THERMOSTAT
FUSE
(Wire leads removed.)
Measure the resistance.
(Multi-meter scale:RX1)
Measure the resistance with 500V-100M
Ohm insulation resistance meter.
Check the continuity of the switch
with an Multi-meter
Normal:
Gill heater
Approx.15 ½
(at 20-30ûC)
Normal:
more than 1.0M ½
NOTE: Make sure heater is fully cooled when tested.
NOTE: If the fuse is blown, check primary, the secondary, the monitor
switches, H.V.D and H.V.C before replacing the fuse.
If the fuse is blown by improper switch operation replace the defective
switch and the fuse at the same time.
Replace just the fuse if the switches operate normally.
0ûC~Approx 180ûC Approx 180ûC
0ûC~Approx 145ûC Approx 145ûC
Normal
Abnormal