Page 2 of 3
For the mounting bracket installation, the receptacle wall box
and Evr-Green mounting bracket must share the same vertical wall
stud
(see Figure 1).
STUD WALL INSTALLATION
48"
12"
EVK02
mounting
bracket
Wall stud
Receptacle
single gang
box
Drywall
Figure 1
Two distinct templates are provided to properly locate the mounting
bracket and receptacle wall box. Using the appropriate template and
following the instructions below will ensure proper installation.
1. Locate a wall stud in the area in which the charging station will be
installed.
2. Measure 48” up from the floor and place a mark horizontally
centered on the stud that will be used for mounting the bracket
and receptacle wall box.
3. Position and affix the mounting template on the wall, aligning the
positioning marks of the template with the mark(s) on the wall.
Ensure the template is level before proceeding
(see Figure 2).
4. Mark the bracket mounting hole locations and the mounting
location for the electrical box. For bare studs, mark the location
for aligning the top of the electrical box. For studded walls with
drywall, mark all four corners of electrical box location.
Electri
c Vehic
le Cha
rger Le
vel 2 -
Installa
tion Te
mplate
Scale:
1 to 1
Ref. C
at. No.
: EVK0
2
Part N
o. DG-
001-EV
K02-20
A-X1
© 2010
Levito
n Mfg.
Co., In
c.
EVK02
mounting
bracket
Mounting
screws
Receptacle
Safety cover
Pilot holes
for mounting
screws
EVB22
mounting
template
Center line
for wall stud
Wall stud
Receptacle
single
gang box
Cut out
for single
gang box
Drywall
Figure 2
EVB22
Installation
Shown
48"
Note: The safety cover will not
be used in the EVB16 application
5. Remove the template. For wood studs, drill two 3/16" diameter
pilot holes, 2-1/2" deep, as indicated for the mounting bracket.
For metal studs, follow manufacturer’s instructions for wall
anchor installation.
6. Secure the mounting bracket to the stud/wall using the two #14 x
2-1/2"L
wood screws provided. Turn the "top" screw into the pilot hole and
drive in
until approximately 1/2" length remains. Hook the bracket onto the
screw using the keyhole slot. Secure in place by installing remaining
screw and tightening first screw.
7. Run an individual circuit as per the National Electric Code and local
building codes. Install the electrical box. For bare stud applications,
align the top of the electrical box with the mark on the stud. For
drywall applications, use keyhole saw to cut the drywall opening
for the electrical box. Position the face of the box flush with the
stud face (for bare stud application) or flush to drywall (for drywall
application). Secure the electrical box to the stud with the screws
provided.
The EVK02 series kit includes a NEMA 6-20 receptacle for cord-
connected charging stations. It accepts back- or side-wiring of
up to #10AWG copper or copper clad wire.
WARNING: TO AVOID FIRE, SHOCK, OR DEATH TURN OFF
POWER
AT CIRCUIT BREAKER OR FUSE AND TEST THAT POWER IS
OFF BEFORE WIRING!
CAUTION: USE THIS DEVICE WITH COPPER OR COPPER
CLAD
WIRE ONLY.
8. Remove insulation per "strip gage" on device. Connect the
receptacle to the electrical wiring as per
Figure 3.
Secure the receptacle to the electrical box using the screws
provided.
NOTE: Receptacle ground opening must be on top (see Figure 3).
9. Turn on the circuit breaker at the main panel and test receptacle
to ensure power is present.
10. If installation for the EVB22, install the safety cover using screws
provided.
NOTE: The hinged side of the safety cover will be at
the bottom of the cover. The safety cover can be locked using
a padlock with a shackle diameter of 3/16" and height of 2-1/2",
such as MasterLock
®
Laminated Padlock No. 7LJ *.
* MasterLock is a registered trademark of Master Lock Company,
LLC.
Figure 3
G
G
240V
Equipment
Ground
6-20R