①
Align the key hole slots in the glides to the T-head pins on both sides of the server, and slide
the mounting glides forward until the pins are secured in the slots.
②
Align the two holes on the mounting glide to the threaded standoffs on the front end of the
server.
③
Secure each mounting glide with two of the M3.5 x 5 mm screws with pre-applied adhesive
that come with the vertical mounting kit.
Step 3. Install one C-channel in the lower portion of the rack cabinet.
Figure 38. Installing the lower C-channel
①
Align the C-channel between the lower rack EIA flanges.
②
Secure the front end of the C-channel to the front EIA flange with
one
M5 x 20 mm screw
through the left most hole in the channel.
③
Secure the rear end of the C-channel to the rear EIA flange with
two
M5 x 20 mm screws
through the right and left most holes in the bracket.
Attention: Do NOT
over-tighten the screws as the rack EIA flange could be deformed.
Step 4. Install the other C-channel in the upper portion of the rack cabinet.
33
Summary of Contents for ThinkSystem Micro DataCenter 6U Acoustic
Page 4: ...ii ThinkSystem Micro DataCenter 6U Acoustic 1200mm Deep Rack Cabinet User Guide ...
Page 10: ...viii ThinkSystem Micro DataCenter 6U Acoustic 1200mm Deep Rack Cabinet User Guide ...
Page 12: ...2 ThinkSystem Micro DataCenter 6U Acoustic 1200mm Deep Rack Cabinet User Guide ...
Page 14: ...4 ThinkSystem Micro DataCenter 6U Acoustic 1200mm Deep Rack Cabinet User Guide ...
Page 24: ...14 ThinkSystem Micro DataCenter 6U Acoustic 1200mm Deep Rack Cabinet User Guide ...
Page 68: ...58 ThinkSystem Micro DataCenter 6U Acoustic 1200mm Deep Rack Cabinet User Guide ...
Page 69: ......
Page 70: ...Part Number SP47A41863 Printed in China 1P P N SP47A41863 1PSP47A41863 ...