Figure 98. Memory module installation
a. Open the memory module connector retaining clips. If a memory module is already installed in
the connector, remove it.
b. Align the keys on the memory module that you are installing with the connector; then, insert the
memory module.
c. Firmly press both ends of the memory module straight down into the connector until the
retaining clips snap into the locked position.
Step 2. If you are installing additional memory modules, do so now.
After you install a memory module:
1. Install the upper system board or system board filler, if it was removed. See “Install a system board” on
2. Install the compute tray where the system board is installed. See “Install a compute tray” on page 117.
3. Install the front cover. See “Install the front cover” on page 132.
4. Power on the system.
5. If you have installed a DCPMM:
a. Update the system firmware to the latest version (see “Firmware updates” on page 19).
b. Make sure that the firmware on all of the DCPMM units is the latest version. If not, update it to the
latest version (see
https://sysmgt.lenovofiles.com/help/index.jsp?topic=
%2Fcom.lenovo.lxca.doc%2Fupdate_fw.html
c. Configure DCPMMs and DRAM DIMMs (see “Configure DC Persistent Memory Module (DCPMM)”
d. Restore the data that have been backed up if necessary.
DC Persistent Memory Module (DCPMM) setup
Follow the instructions in this section to complete required setup before installing DCPMMs for the first time,
determine the most suitable configuration, and install memory modules accordingly.
178
User Guide for ThinkAgile VX7820 Appliance, ThinkAgile VX 4-Socket 4U Certified Node
Summary of Contents for ThinkAgile VX 4-Socket 4U Certified Node
Page 6: ...iv User Guide for ThinkAgile VX7820 Appliance ThinkAgile VX 4 Socket 4U Certified Node ...
Page 10: ...viii User Guide for ThinkAgile VX7820 Appliance ThinkAgile VX 4 Socket 4U Certified Node ...
Page 69: ...Chapter 2 Server components 59 ...
Page 76: ...66 User Guide for ThinkAgile VX7820 Appliance ThinkAgile VX 4 Socket 4U Certified Node ...
Page 96: ...86 User Guide for ThinkAgile VX7820 Appliance ThinkAgile VX 4 Socket 4U Certified Node ...
Page 252: ...242 User Guide for ThinkAgile VX7820 Appliance ThinkAgile VX 4 Socket 4U Certified Node ...
Page 276: ...266 User Guide for ThinkAgile VX7820 Appliance ThinkAgile VX 4 Socket 4U Certified Node ...
Page 284: ...274 User Guide for ThinkAgile VX7820 Appliance ThinkAgile VX 4 Socket 4U Certified Node ...
Page 295: ......
Page 296: ......