© Copyright Lenovo 2016
Chapter 2: Installing and Removing the SI4091
19
8.
Push the release levers on the front of the switch to the closed position. After you
insert and lock the switch, it is turned on (there may be a slight delay), and a
Power-On Self-Test (POST) occurs to verify that the switch is operating correctly.
Note:
The switch may take up to two minutes to complete the POST. During
POST, the Power LED continuously flashes. Once POST has successfully
completed, the Power LED remains on and the Error LED is off.
9.
Make sure that LEDs on the switch indicate that it is operating correctly (see
10.
If you have another switch to install, repeat
through
; otherwise, go to
the next step.
11.
Install any port transceiver modules or Direct-Attach Cables (DACs) needed for the
switch. For information and instructions, see
and the documentation that comes with the transceiver modules or DACs.
12.
Attach any cables that are required by the switch. For additional information about
cabling the switch, see
“Connecting Switch Ports” on page 21
, the documentation
that comes with the port transceiver modules, DACs, cables, and the optional
network devices to which the cables are connected.
13.
Make sure that the data (non-management) ports on the switch are enabled
through the Chassis Management Module (CMM).