background image

Page 16

IV−CHARGING 

Units are factory charged with the amount of R−410A refrig-
erant indicated on the unit rating plate. This charge is
based on a matching indoor coil and outdoor coil with 15 ft.
(4.6m) line set. For varying lengths of line set, refer to table
8 for refrigerant charge adjustment.

TABLE 8

Liquid Line Set

Diameter

Ozs. per 5 ft. (grams per 1.5m) adjust 

from 15 ft. (4.6m) line set*

3/8 in.

(10mm)

3 ounces per 5 feet

(85g per 1.5m)

*If line length is greater than 15 ft. (4.6m), add this amount.
If line length is less than 15 ft. (4.6), subtract this amount.

A−Leak Testing

After the line set has been connected to the indoor and out-
door units, the line set connections and indoor unit must be
checked for leaks.

WARNING

Refrigerant can be harmful if inhaled. Refrigerant
must be used and recovered responsibly. Failure
to follow this warning can lead to injury or death.

WARNING

Fire, Explosion and Personal Safety Hazard.
Failure to follow this warning could result in damage,
personal injury or death.
Never use oxygen to pressurize or purge refrigera-
tion lines. Oxygen when exposed to a spark or open
flame can cause damage by fire and or an explosion,
that could result in personal injury or death.

WARNING

Danger of explosion:  Can cause equipment damage,
injury or death. When using a high pressure gas
such as dry nitrogen to pressurize a refrigeration or
air conditioning system, use a regulator that can
control the pressure down to 1 or 2 psig (6.9 to 13.8
kPa).

Using an Electronic Leak Detector

 1 − Connect a cylinder of R−410A to the center port of the

manifold gauge set.

 2 − With both manifold valves closed, open the valve on

the R−410A  cylinder (vapor only).

 3 − Open the high pressure side of the manifold to allow

the R−410A  into the line set and indoor unit. Weigh in a
trace amount of R−410A .

 

[A trace amount is a maxi-

mum of 2 ounces (57 g) or 3 pounds (31 kPa) pres-
sure.]

 

Close the valve on the R−410A  cylinder and the

valve on the high pressure side of the manifold gauge
set. Disconnect the R−410A  cylinder.

 4 − Connect a cylinder of nitrogen with a pressure regulat-

ing valve to the center port of the manifold gauge set.

 5 − Connect the manifold gauge set high pressure hose to

the vapor valve service port. 

(Normally, the high pres-

sure hose is connected to the liquid line port; however,
connecting it to the vapor port better protects the man-
ifold gauge set from high pressure damage.)

 6 − Adjust the nitrogen pressure to 150 psig (1034 kPa).

Open the valve on the high side of the manifold gauge
set which will pressurize line set and indoor unit.

 7 − After a few minutes, open a refrigerant port to ensure

the refrigerant you added is adequate to be detected.
(Amounts of refrigerant will vary with line lengths.)
Check all joints for leaks. Purge nitrogen and R−410A
mixture. Correct any leaks and recheck.

IMPORTANT

Leak detector must be capable of sensing HFC re-
frigerant.

B−Evacuating

Evacuating the system of noncondensables is critical for
proper operation of the unit. Noncondensables are defined
as any gas that will not condense under temperatures and
pressures present during operation of an air conditioning
system. Noncondensables and water vapor combine with
refrigerant to produce substances that corrode copper pip-
ing and compressor parts.

IMPORTANT

Use a thermocouple or thermistor electronic vacuum
gauge that is calibrated in microns. Use an instrument
that reads from 50 microns to at least 23,000 microns.

 1 − Connect the manifold gauge set to the service valve

ports as follows:

 

 

low pressure gauge to 

vapor

 line service valve

 

 

high pressure gauge to 

liquid 

line service valve

 2 − Connect micron gauge.

 3 − Connect the vacuum pump (with vacuum gauge) to the

center port of the manifold gauge set.

 4 − Open both manifold valves and start vacuum pump.

 5 − Evacuate the line set and indoor unit to an 

absolute

pressure

 of 23,000 microns (29.01 inches of mercu-

ry). During the early stages of evacuation, it is desir-
able to close the manifold gauge valve at least once to
determine if there is a rapid rise in 

absolute pressure

.

A rapid rise in pressure indicates a relatively large leak.
If this occurs, repeat the leak testing procedure.

NOTE − The term absolute pressure means the total
actual pressure within a given volume or system,
above the absolute zero of pressure. Absolute pres-
sure in a vacuum is equal to atmospheric pressure mi-
nus vacuum pressure.

 6 − When the absolute pressure reaches 23,000 microns

(29.01 inches of mercury), close the manifold gauge
valves, turn off the vacuum pump and disconnect the
manifold gauge center port hose from vacuum pump.

Summary of Contents for HPXA16 series

Page 1: ...ice equipment rated for R 410A WARNING Improper installation adjustment alteration service or maintenance can cause property damage person al injury or loss of life Installation and service must be pe...

Page 2: ...230V 1ph 208 230V 1ph 208 230V 1ph 3 Maximum overcurrent protection amps 20 35 45 60 2 Minimum circuit ampacity 13 7 22 1 28 2 33 8 Compressor Rated load amps 10 3 16 7 21 2 25 7 p Locked rotor amps...

Page 3: ...NG SCROLL DISCHARGE SUCTION CROSS SECTION OF SCROLLS TIPS SEALED BY DISCHARGE PRESSURE DISCHARGE PRESSURE The counterclockwise orbiting scroll draws gas into the out er crescent shaped gas pocket crea...

Page 4: ...operate on first stage until demand is satisfied or the indoor temperature reaches the thermostat set point calling for second stage Second stage high capacity is achieved by blocking the bypass port...

Page 5: ...tch Procedure 1 Turn main power OFF to outdoor unit 2 Adjust room thermostat set point above heating op eration on heat pump or below cooling operation the room temperature 5 F 3 Remove control access...

Page 6: ...ltage at the female connector end of the full wave rectifier plug The DC voltage reading should be 1 5 to 3 volts lower than the input voltage to the plug wire leads EX Input voltage is 24VAC output v...

Page 7: ...y will allow moisture to en ter the bearing resulting in motor failure See figure 9 FIGURE 8 A SEE TABLE 2 FAN GUARD Condenser fan and motor Wiring Drip loop TABLE 2 HPXA16 UNIT A DIM 1 8 024 036 1 1...

Page 8: ...ss re frigerant condensed liquid from the indoor coil is trapped by the compensator The vapor line is cooler than the liquid line so liquid migrates from the liquid line to the compensa tor tank where...

Page 9: ...s for a fifth time during the current Y1 Input the control will enter a lockout condi tion The 5 strike pressure switch lockout condition can be reset by cycling OFF the 24 volt power to the control b...

Page 10: ...d recognizes five temperature sensor range faults during a single Y1 compressor demand it re verts to a lockout mode and displays the appropriate code The board detects open sensor or out of tem perat...

Page 11: ...ast defrost cycle while the coil tempera ture remains below 35 F 2 C the demand defrost control will initiate a defrost cycle Actuation When the reversing valve is de energized the Y1 circuit is energ...

Page 12: ...r will check for ambient and coil faults open or shorted If a fault exists the unit will remain in Heat Mode and no further test mode operation will be executed until the test short is removed and re...

Page 13: ...nection to sys tem have secure connections to system to prevent refrigerant leaks or errors in pressure and temperature measurements SLOW Flash ON Discharge Line Tempera ture Fault This code detects s...

Page 14: ...The reversing valve is energized during cooling de mand and during defrost III REFRIGERANT SYSTEM Field refrigerant piping consists of liquid and vapor lines from the outdoor unit sweat connections U...

Page 15: ...for liquid line size 3 Replace stem cap and tighten it firmly Tighten finger tight then tighten an additional 1 6 turn To Close Service Valve 1 Remove stem cap with an adjustable wrench 2 Using servic...

Page 16: ...he vapor valve service port Normally the high pres sure hose is connected to the liquid line port however connecting it to the vapor port better protects the man ifold gauge set from high pressure dam...

Page 17: ...in the heating season one of the following proce dures must be followed to ensure proper system charge Weighing in the Charge TXV Systems Outdoor Temp 65 F 18 C If the system is void of refrigerant o...

Page 18: ...d indicate that the system is overcharged Pressures lower than those listed indicate that the system is undercharged Verify adjusted charge using the approach method Approach Method 4 Use the same dig...

Page 19: ...Vapor 65 18 3 222 143 244 136 232 134 249 126 75 23 9 256 145 282 139 266 136 289 134 85 29 4 302 145 325 142 309 139 330 140 95 35 0 349 147 377 144 359 142 378 143 105 40 6 403 149 428 146 410 144 4...

Page 20: ...5 506 5 43 125 0 74 214 0 105 340 5 136 512 9 44 127 3 75 217 4 106 345 3 137 519 3 45 129 7 76 220 9 107 350 1 138 525 8 46 132 2 77 224 4 108 355 0 139 532 4 47 134 6 78 228 0 109 360 0 140 539 0 48...

Page 21: ...m POE oil VI MAINTENANCE WARNING Electric shock hazard Can cause inju ry or death Before attempting to per form any service or maintenance turn the electrical power to unit OFF at dis connect switch e...

Page 22: ...Page 22 VII DIAGRAM OPERATING SEQUENCE...

Page 23: ...ost board sends 24 volts through Y1 OUT signal to the K1 compressor contactor coil 3 The defrost board sends 24 volts through Y2 OUT to the L34 compressor solenoid plug The 2 wire com pressor solenoid...

Reviews: