1. Turn hitch and weight tray upside down and orient as
shown. Position end panel (#1A) on the left end of the
weight tray to begin assembly of the rotor shaft.
2. Insert rotor shaft (#5) in end panel (#1A)
3. Install 1" flat washer (#6A), gang assembly (#2A),
1" flat washer (#6), spacer (#4), and second flat
washer (#6) on rotor shaft (#5).
4. Install gang assembly (#2B), 1" flat washer (#6),
center support (#3), and second flat washer (#6) on
the rotor shaft.
IMPORTANT:
Make sure all gang assemblies (#2)
are installed on rotor shaft (#5) with the open side of
the spoons facing forward in rotation as shown.
5. Install gang assembly (#2C), 1" flat washer (#6),
spacer (#4), and second flat washer (#6) on the rotor
shaft.
6. Install gang assembly (#2D), 1" flat washer (#6),
spacer (#4), and second flat washer (#6) on the rotor
shaft.
7.
Install gang assembly (#2E), 1" flat washer (#6),
center support (#3), and second flat washer (#6) on
the rotor shaft.
8. Install gang assembly (#2F), 1" flat washer (#6),
spacer (#4), and second flat washer (#6) on the rotor
shaft.
9. Install gang assembly (#2G) and 1" flat washer (#6B)
on the rotor shaft.
10. Install end panel (#1B) on the right end of the rotor
shaft (#5).