BEV85 Annual Operational Service 
Work Instruction 

 

www.lancerbeverage.com

 

Page 4 of 4 

Images are for illustration purposes only as product may vary. 

No 074  

–  1 November 2018

 

19 

Replace cylinder head 
assembly 

 

20 

Tighten all 12 head bolts 

Follow tensioning pattern 
 
Hand tighten each bolt, 
clockwise, extra leverage is 
not required.  
 
Each bolt has a spring 
washer, fitted to assist with 
securing the fixing. 
 
Aluminum threads strip easily.  

 

 

21 

Connect High Pressure 
hose 

Using a Spanner, Turn anti-
Clockwise to tighten hose 
fitting. 

 

 

22 

Replace heat covers 

      PH2 Phillips heads  
      2 x heat covers 
 
Replace heat covers, secure 
each with 2 fixing screws. 

 

23 

Re-connect and energise 
the electrical supply to the 
air compressor 

 

Plug electrical lead into socket 
outlet and lift red button on 
pressure switch to turn on the 
air compressor. 

 

24 

Check for air leaks 

Monitor the tank pressure 
gauge, listen for leaking air 
(hissing) and/or use soapy 
water to inspect air fittings, 
pipe joints & connections. 
 

 

Compressor will run for about 
1 minute 30 second before 
cycling off. 
 
 

 

Check the NRV Operation 

When the compressor 
reaches its cut-out pressure 
there should be a shot of air 
from underneath the pressure 
switch. If this shot of air is not 
evident or the air continually 
leaks replace the Non-Return 
Valve Seal & Spring. 

 

 

25 

Test auto-drain 

Press the “TEST” button on 
the Auto Drain which should 
release a burst of air and then 
stop.  
If this does not work have the 
compressor checked by an 
approved service agent. 

 

26 

Re-connect air supply 

Turn the supply air tap on, ¼ 
turn. Handle will be in line with 
the hose.  
This is the red handle.  

 

27 

Change Over to 
Compressed Air supply 

Switch main Beverage Control 
Panel over to Compressed air 
supply from CO2 supply.  
 

 

 

 