INSTALLER’S MANUAL
Recommendations :
Ensure that the oven is set to the type of gas used (see label on the gas connector).
If the gas supply is not compatible with the gas setting of your range the setting must be modified. Refer
to the “Changing gas type” section of the present instructions.
Butane-fuelled units
: Connect unit to 2.6 kg/h pressure reducer. Use two cylinders connected to a 3-way
valve ahead of the pressure regulator in case of prolonged, continuous duty.
Propane-fuelled units
: Connect unit to a 3.0 kg/h pressure reducer. Use two cylinders and a 3-way
valve ahead of the pressure regulator in case of prolonged, continuous duty. The use of 37 kg or external
cryogenic tanks is both possible and recommended.
Before connection :
Check
:
◊
That the gas supply pressure matches the gas pressure for which the range is set.
◊ Pipework is perfectly clean in order to prevent the injectors becoming blocked and malfunctioning of
the magnetic heads.
◊ The gas for which the appliance was set up : rating plate and markings.
◊ Cross-sectional area of gas supply pipework is compatible with the appliance’s thermal output.
◊ Correct fresh air flowrate (air supply sufficient to enable correct combustion to occur
(see appendix 1).
Gas connection :
Male coupling Ø 15/21, 1/2” gas thread on ( see
A
/ figure
1
).
After connection :
Check the mains pressure at (see
B
/ figure
2
).
Check your connection is gastight.
B
A
1
2
GAS CONNECTION
Sully - Ft 124a - GB - Rév 06 - Modifié le : 07/10/2013 11/42