6.3 Shutdown/storage/preservation
6.3.1 Measures to be taken for shutdown
The pump (set) remains installed
✓
Sufficient fluid is supplied for the operation check run of the pump.
1.
Start up the pump (set) regularly between once a month and once every three
months for approximately five minutes during prolonged shutdown periods.
This will prevent the formation of deposits within the pump and the pump
intake area.
The pump (set) is removed and stored
✓
The pump has been properly drained
instructions for dismantling the pump have been observed.
1.
Spray-coat the inside wall of the pump casing, and in particular the impeller
clearance areas, with a preservative.
2.
Spray the preservative through the suction and discharge nozzles.
It is advisable to then close the pump nozzles (e.g. with plastic caps or similar).
3.
Oil or grease all exposed machined parts and surfaces of the pump (with
silicone-free oil or grease, food-approved, if required) to protect them against
corrosion.
Observe the additional instructions.
If the pump set is to be stored temporarily, do not preserve the wetted components
made of alloy materials.
Observe any additional instructions and information provided.
6.4 Returning to service
For returning the pump to service observe the sections on commissioning/start-up
In addition, carry out all servicing/maintenance operations before returning the
pump (set) to service.
WARNING
Failure to re-install or re-activate protective devices
Risk of personal injury from moving parts or escaping fluid!
▷
As soon as the work is complete, re-install and/or re-activate any safety-relevant
and protective devices.
NOTE
If the pump has been out of service for more than one year, replace all elastomer
seals.
6 Commissioning/Start-up/Shutdown
36 of 62
Etachrom NC