![KRAL CGF Operating Instructions Manual Download Page 55](http://html.mh-extra.com/html/kral/cgf/cgf_operating-instructions-manual_2000364055.webp)
15 Accessories
15.2 Overflow valve
It therefore has to be ensured through a safety valve at the system that the maximum operating pres-
sure always lies under the opening pressure of the overflow valve.
The overflow valve is offered as a circulation valve (figure left) or as a non-return valve (figure right).
Notice
o
A function test of the overflow valve at least every 5 years is essential for the safe operation
Ä
o
Scope and if necessary shorter test intervals must be specified by the operator-owner in accord-
ance with the requirements and national provisions (for example Austrian Ordinance of Safety and
Health (BetrSichV)).
o
The first function test must take place directly after the commissioning.
o
After longer downtimes (> 4 weeks) the function of the overflow valve must be tested again.
15.2.1
Adjusting the overflow valve
Personnel qualification:
o
Fitter
Aids:
o
Hexagon key
Notice
The opening pressure of the overflow valve is set to 110% of the differential pressure in the factory.
2
2
1
2
1
1
Fig. 16: Overflow valve
1
Screw plug/cap
2
Adjusting screw
WARNING
Risk of injury through emitted pumped liquid.
Pumped liquids can be hot, poisonous, combustible and caustic.
► Wear personal protective clothing during all the work. Ensure face protection.
► Collect any discharging pumped liquid safely and dispose of it in an environmentally compatible
manner in accordance with the applicable local regulations.
Requirement:
ü
Pressure-side pressure gauge installed
1.
Switch on the pump and remove the screw plug/cap
1
of the overflow valve.
2.
Increase the supply pressure step-by-step to check the opening pressure of the overflow valve.
Keep an eye on the pressure gauge and make sure that the operating limits are observed.
ð
The opening pressure is reached, when the displayed pressure falls.
3.
Turn the adjusting screw
2
to set the opening pressure:
Turning clockwise: Increase the opening pressure
Turning counter-clockwise: Reduce the opening pressure
4.
Repeat Steps 2 and 3 until the desired opening pressure is reached.
5.
Tighten the screw plug/cap
1
again.
Operating instructions