VI. Pre-Installation Testing

Before mounting the air conditioner to the enclosure, test for proper operation. This will verify the
shipping integrity of the system. Please follow the steps below prior to installation.

CAUTION

1. Allow the unit to sit in a upright position at a room temperature of 65°F minimum, allowing the

system to warm-up. This is particularly important in winter months.

2. Refer to the nameplate for proper electrical voltage and current requirements. Then connect the

power cord to a properly grounded and fused electrical supply. Leave the electrical power off.

3. Note the factory thermostat setting which is typically 75 to 80°F.

4

Adjust the thermostat to its maximum setting.

5. If the unit is equipped with an on-off switch, move it to the on position.  

6. Turn electrical power on.

7. Verify that the evaporator blower or fan is running.

8. Adjust the thermostat to its minimum setting. The compressor should start. On units equipped with

a short cycle protector, the compressor will have a delayed start of six (6) minutes from the time
the power is applied to the unit.  

9. Verify that the condenser blower or fan is running.  Note that on units equipped with a low ambient

kit, the start of the condenser fan or blower will be delayed until the system pressures rise.

10. Operate the air conditioner for approximately ten (10) minutes. During this period no unusual noise

or vibration should be evident. Both the evaporator and condenser fans or blowers should be
delivering air through their respective discharge ports. The cool air discharged should be less than
70°F when the room temperature is between 70 and 80°F.  

11. On units equipped with heaters, adjust both the cooling and heating thermostats to their maximum

settings. Verify that the compressor and condenser fan or blower has stopped. Verify elevated
discharge air temperature from the evaporator air discharge.

12. If the unit is equipped with an on-off switch, leave it in the on position. Return the cooling

thermostat to its original setting. If the unit is equipped with a heater, return the heating thermostat
to its original position. 

13. Turn off the electrical power source, and disconnect the air conditioner from the power source.

14. If any cover plug is removed to adjust the unit, make certain to put it back in place to maintain the

integrity of the closed-loop airflow system.

NOTE:

Before shipment all Kooltronic, Inc. Air Conditioners are subjected to a performance test.

The Air Conditioner must be standing in its proper mounting position for a

minimum of five (5) minutes prior to testing. Failure to follow this procedure

will cause permanent damage to the compressor.

Summary of Contents for K2A4C2WNP28

Page 1: ...S IMPORTANT THAT THIS MANUAL BE READ AND UNDERSTOOD THOROUGHLY KOOLTRONIC INC 30 Pennington Hopewell Road Pennington NJ 08534 609 466 3400 FAX 609 466 1114 www kooltronic com TRIMLINE WNP28 SERIES 900...

Page 2: ...age of the Kooltronic website I Introduction Kooltronic Air Conditioners are designed to provide a cool dehumidified environment for your electronic components There are models to fit virtually all si...

Page 3: ...prior to operating in order to allow the compressor oil to drain to the compressor sump area CAUTION 3 Before operating this unit all electrical wiring must be checked to assure the proper connection...

Page 4: ...Final Assy Number MFG Order Number e Before operating be sure that the power source matches these requirements y Use of incorrect type or amount of refrigerant will adversely affect performance and ma...

Page 5: ...ession refrigeration cycle This takes place in a hermetically sealed refrigeration system utilizing either an air cooled or water cooled condenser heat exchanger The warm air inside the enclosure is d...

Page 6: ...blower will be delayed until the system pressures rise 10 Operate the air conditioner for approximately ten 10 minutes During this period no unusual noise or vibration should be evident Both the evap...

Page 7: ...e top cut out in your cabinet Mount the unit to the M TAB by sliding the 4 studs on the side panel into the 4 slots on the M TAB After unit is in place tighten 2 screws at bottom of unit These two scr...

Page 8: ...ATER INLET 3 8 18 NPT MALE FITTING DRAIN 63 16 1 4 01 101 9 28 50 723 9 THERMOSTAT ADJUSTMENT 1 1 2 Drawings and Dimensions WNP28 SERIES Other drain outlets are available contact KOOLTRONIC Dimensions...

Page 9: ...ater temperature 115V 60 Hz and 230V 60 Hz models also perform at full capacity when operated at 100V 50 Hz or 200V 50 Hz respectively No transformer is required KA4C2WNP28 2000 1 0 115 100 60 50 13 0...

Page 10: ...nd the compressor will continue to cycle on and off Continued operation under these conditions will cause damage shorten compressor life and void the warranty A Filter Removal and Service Kooltronic A...

Page 11: ...ypass valve fails it is strongly recommended that the Air Conditioner be returned to Kooltronic for service D Refrigerant Loss Kooltronic Air Conditioners are subjected to a series of tests to detect...

Page 12: ...applicable Failed Compressor Replace Compressor Ice on Evaporator Coil Insufficient Heat Load or Unit Contact Kooltronic Oversized for Application Failed Evaporator Blower Replace Evaporator Blower Mo...

Page 13: ...nal customer Purchase Order number and date Date product was received by customer Number of parts to be returned Product description model and serial number Reason for return Action requested Contact...