Procedure
1
Obtain the necessary lifting equipment, and make sure that the equipment is
certified for the weight.
2
Lift the transducer, sonar head or hydrophone out of the transportation box.
3
Place it in a stable position on the floor/work bench.
4
Inspect the unit for visual damage.
5
Make sure that the relevant protection is kept in place until the final stages of the
installation.
6
Collect and keep the relevant user manuals and/or documents provided with the unit.
7
Observe the handling rules for transducers.
EM 2040C
Summary of Contents for EM 2040C
Page 1: ...Maintenance manual EM 2040C Multibeam echo sounder...
Page 2: ......
Page 3: ...378511 A August 2016 Kongsberg Maritime AS EM 2040C Multibeam echo sounder Maintenance manual...
Page 8: ...6 378511 A EM 2040C...
Page 16: ...14 378511 A Troubleshooting Topics BIST Built In Self Test dialog box page 15 EM 2040C...
Page 71: ...378511 A 69 Hydrographic Work Station outline dimensions Drawing 378828 2 pages Drawing file...
Page 72: ...70 378511 A Page 2 EM 2040C...
Page 124: ...2016 Kongsberg Maritime...