11. INSTALL APRONS
Locate the screws removed during bath inspection.
This apron system is designed to have the finished wall
materials go over the apron columns. It is also designed
to have the finished floor materials butt up against the
pan base.
Slip the top of an apron up into the channel groove. Tilt
the apron inward. Align the bottom of the apron with the
pan base. The apron should align with both the bath rim
and the edges of the apron columns, and with the
predrilled holes in the pan base.
Secure the apron to the pan base with screws.
Repeat for other apron.
Supplied Drywall Screw
Large Apron
Small
Apron
Supplied Drywall
Screws
12. INSTALL FINISH WALL
Protect the inside of the bath to prevent damage.
Construction damage is not covered under
warranty!
NOTICE: Before covering the framing, perform the
following: Open hot and cold valves and check all
supply connections for leaks. Fill the bath to the overflow
and check overflow and drain connections for leaks.
Protect bath surface. Cover framing and walls with
gypsum wallboard. Tape and mud drywall... seal drywall
and joints under bath rim. Install finished wall material
to subwall. Seal joints between the bath rim and finished
wall using silicone sealant.
Stud
Gypsum
Wallboard
Finished Wall
Covering
RTV Water
Resistant
Sealer
Bath