7
1012557-2-
A
Kohler Co., Kohler, WI U.S.A.
4. VALVING CHECKOUT (ALL INSTALLATIONS)
Thread a 1/4” pipe plug into the top of the spout supply
tube.
Ensure that the valves are closed (cold - fully
counterclockwise, hot - fully clockwise).
Turn on the main water supply, and check the complete
installation for leaks with the valves closed and open.
Repair leaks as required.
Close both valves. Turn off the main water supply.
1/4” Pipe Plug
Close
Cold
Close
WARNING: Risk of personal injury. Lines will be
pressurized. Do not lean over pipe plug when
turning or removing the plug.
Close
Hot
Wrap a towel around the pipe plug to prevent water spray.
Water will purge from the supply tube when you remove
the plug.
Carefully back out the pipe plug to relieve pressure.
Thread the pipe plug back into the spout supply tube.
Leave the pipe plug installed until the spout and handle
are installed.
Install the cardboard plaster guards over both valves and
the spout supply tube. Leave in place until the spout and
handle are installed.
Fig. #13
5. INSTALL TILE (IF APPLICABLE)
Verify that there will be a 1-1/4” (3.2cm) distance from the
top of the sleeve to the top of the tile. If not, do not install
the tile due to improper valve installation.
If proper clearance exists, install tile up to the plaster
guards on the valves and the spout supply tube.
Fig. #14
Threaded
Collar
Rough
Deck
Tile
Spout
Supply
Tube