Installation
9
Electrical Operation Test
13.Reconnect the contactor control in-line
disconnect plugs. See Figure 8.
The transfer switch should be in the
normal position. The following procedure
will check the electrical operation of the
transfer switch.
14.Open the normal source circuit breaker to
start the generator set, or start the
generator set at the generator set
controller. See Figure 9. The generator set
should start after any engine-start time
delay set in the transfer switch and/or
generator set controller has completed
timing.
15.Allow the generator set to stabilize at its
rated voltage.
Figure 8. In-Line Disconnect Plug