TESTING FOR EMERGENCY LUMINAIRES

Recommended routine test procedure in accordance with BS5266.

Initial commissioning test - We recommend a minimum charge period of 24 hours before completing 
an initial commissioning emergency duration test

Daily check – check that the status GREEN LED indicator is illuminated.

Monthly functional test – simulate a mains supply failure for approx. 30 secs by operation of key 
switch or switching off a circuit breaker.  Ensure normal supply is restored after test and the indicator 
status LED is illuminated.

Annual full three hour duration test - conduct a three hour continuous duration test.  Simulate a 
mains supply failure for three hour continuous test by operation of key switch or switching off circuit 
breaker.  Ensure normal supply is restored after test and the indicator status LED is illuminated.

If the luminaire fails any of the above tests, please contact a qualified electrician. 

TEST RECORD SHEET

 

INITIAL COMMISSIONING

3 HOUR TEST

SIGNED

DATE

MONTH

TEST

FIRST YEAR

SECOND YEAR

THIRD YEAR

FOURTH YEAR

FIFTH YEAR

SIGNED

DATE

SIGNED

DATE

SIGNED

DATE

SIGNED

DATE

SIGNED

DATE

1

FUNCTIONAL

2

FUNCTIONAL

3

FUNCTIONAL

4

FUNCTIONAL

5

FUNCTIONAL

6

FUNCTIONAL

7

FUNCTIONAL

8

FUNCTIONAL

9

FUNCTIONAL

10

FUNCTIONAL

11

FUNCTIONAL

12

3 HOUR

Installed by: 

Installation date:

Contact number:

Reviews: