KNIGHT SMART CART OPERATION MANUAL
SECTION 4
MAINTENANCE
32
Step 11. While supporting the chain buckets, remove the (1) one M5 retainer bolt that
secures both chain buckets inside of the Servo Hoist. (Refer to Figure 4-17)
Figure 4-17
Step 12. Turn the cart’s power ON.
Step 13. Press the down button.
Step 14. Stop the movement of the chains when the yellow interface chain links have moved
through the gear box and are at an acceptable height to reattach the cart’s trolley.
Step 15. Lubricate both the load and the Safety Drop Stop (SDS) chains per section
4.4.3 ‘Chain Lubrication’.
Step 16. Reinstall both chains into each of their correct chain buckets.
Step 17. Reinstall the chain buckets back to the mast.
Step 18. The SDS chain needs to be cut to the correct length so it has slack in it when the
load chain is properly connected.
Step 19. Ensure that both chains are parallel with no twists from the gear box down to their
respective ends.
Step 20. Count down FOUR links from the end of the load chain.
Cut the FIFTH link so the SDS chain is FOUR links longer than the load chain.
Step 21. Install the safety chain identification sleeve on the SDS chain and then heat shrink it
to the SDS chain on the eighth link up from the bottom of the SDS chain.
(Refer to Figure 4-18)
Figure 4-18