9
Framing
(The following method assumes that framing is in place
before
the unit is installed.)
Using 2x4’s, frame to local building codes.
DO NOT
install against a Vapor Barrier or Exposed Insulation.
Framing measurements have been adjusted to accommodate a ½” thick finished wall. Combustible materials may be installed flush with
the top and sides of the installed CVCK Kits.(See Page 10, “Framing and Facing Requirements.)
It is not necessary to install a hearth with this fireplace system. Objects placed in front of the fireplace should be kept a minimum of 24”
away from the front face.
Gas line installation should be performed only after fireplace installation. Fireplace bottom supplies you with two 6” x 8” rectangular
holes. The use of these holes depends on valve and fireplace location on riser or upper floor.
Fireplace Assembly
1.
Mount Door Cover.
First apply a bead of High Heat Silicone to door seal. Mount Door Cover and screw into place, making
sure that door is properly sealed.
2.
Hang Heat Shield on top edge of fireplace; secure with self
-
tapping screws
. Heat Shield must be centered, allowing a
½” clearance both sides of fireplace.
3.
Top Door Shield
should be installed on both sides of unit when the doors are installed.
4.
Place unit inside framing and center.
You are now ready to install CVCK Kits onto unit (See page 11).Gas line and
electrical connections (blower fan, etc.) should be performed at this time.
5. Once the unit (with CVCK Kits) is installed into Framing, Facing Material may be installed (See page 10)
.
See-Thru With CVCK Installation
Summary of Contents for MDV30
Page 19: ...17...
Page 41: ...39 For Models MDV31 39 Replacement Parts continued...